An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. nSQP Deliverables Dates D. Giugni October 7th , 2010 NSQP

  2. General • Material procurement is based on 10 NSQP’s • 1 Prototype SQP • 8 Production SQP’s • 1 full set of spare parts • Actually working on the procurement plan with all the details about who and when. For now I have extracted the basic info... NSQP

  3. Milestones DeliverablesProviderDelivery Dates First prototype SQP (parts for) 06/2011 • Final Design Review (end of) 01/2011 • Carbon structures panels (2OSP+2ISP), and 1 longeron [LBL] 02/2011 • SLA parts [CERN] 02/2011 • Harnesses (LV, NTC-OPTO and HV) [CERN] 05/2011 • Penetration Flexes [CERN] 03/2011 • PP0 boards [CERN] 03/2011 • PP0 flexes (12) [LBL] 03/2011 • Alu Pipes, Hex, Capillaries [CERN] 03/2011 • Electrical Repeater harnesses (36) [SLAC] 05/2011 First SQP qualified 07/2011 NSQP

  4. SQPS Production DeliverablesProviderDelivery Dates • Production SQP (8articles) 10/201101/2012 • Rest of the carbon structures (18OSP, 18ISP, 9 longerons) [LBL] 09/2011 • SLA parts [CERN] 09/2011 • Harnesses (LV, NTC-OPTO and HV) [CERN] 05/201108/2011 • Penetration Flexes [CERN] 05/2011 • PP0 boards [CERN] 05/2011 • PP0 Flexes (108) [LBL] 05/2011 • Alu Pipes, Hex, Capillaries [CERN] 05/2011 • Electrical Repeater harnesses (324) [SLAC] 08/2011 • Last SQP 01/2012 NSQP

  5. Off Detector Deliverables Provider Delivery Dates • OptoBoards [OSU] • First batch of 40 05/2011 • Second batch (can go in several batches) up to 05/2012 • Type II cables/services [CERN?] • ~ 300 Type II VVDC cables (OptoBox PP2) 02/2012 • ~ 300 Type II NTC-OPTO 02/2012 • Optofibers termination [CERN] 05/2012 • New LV PP2 boxes (1+1) [CERN?] 02/2012 NSQP

  6. Major tooling/facilities DeliverablesDelivery Dates • Assembling Area Ready 02/2011 • Pin tables (batches) 01/1011 • Electrical Testing setup 02/2011 • ITT (Integration and Testing Tool) 03/2012 • DST (Dummy Support Tool) 04/2012 NSQP

  7. Short time deliverables • There are few changes that must be done on the actual SQP design. We try to keep everything like it is except what must be modified. • Electrical readouts • Cable routing parts (SLA) • Removal of the cooling loop dedicated to the opto’s • I’d like to pre-assembly a SQP’s with all the parts that are available (LBLCERN) in a very short time. Still needs: • 2 OSP Corrugated panels (LBL) 11/2010 • 1 longeron (LBL) 11/2010 • PP0 flexes (LBL) in hands • PP0 boards (LBL) in hands NSQP