Title V Oil and Gas General Operating Permits. Whitney Hill Air Permits Division Texas Commission on Environmental Quality Environmental Trade Fair 2014. Objectives. Learn the differences between a GOP and a SOP Learn the technical review procedures for an ATO application
E N D
Title V Oil and Gas General Operating Permits Whitney Hill Air Permits Division Texas Commission on Environmental Quality Environmental Trade Fair 2014
Objectives • Learn the differences between a GOP and a SOP • Learn the technical review procedures for an ATO application • Learn the procedures for a GOP renewal or revision The difference between a GOP and a SOP. The procedures for a GOP renewal or revision. Technical review procedures for an ATO application.
Types of Title V Permits • Site Operating Permit (SOP) • General Operating Permit (GOP) • Oil & Gas: 511, 512, 513, 514 • MSW Landfill: 517 • Air Curtain Incinerator: 518
Important Terminology GOP: The documents that contain all permit requirements for the industry type. ATO: Authorization to operate under a general operating permit.
GOPs vs. SOPs • General requirements • De minimis, standard permits, & PBRs only • No public notice/EPA review done by TCEQ • Site specific review • Compliance plans allowed • Public notice/ EPA review for each site • FOPs • Renewed every 5 years • Legislative notification • General requirements • De minimis, standard permits, & PBRs only • No public notice/EPA review for ATO • Site specific review • Compliance plans allowed • Public notice/ EPA review for each site • FOPs • Renewed every 5 years • Legislative notification
Permit Content • ATO Letter • GOP Cover Letter • GOP Terms • GOP Tables • CAM/PM (if applicable) • Statement of Basis • Application (federally enforceable) • ATO Letter • GOP Cover Letter • GOP Terms • GOP Tables • CAM/PM (if applicable) • Statement of Basis • Application (federally enforceable)
Initial ATO Application Procedure • Qualify • Required information • Forms • Applicable requirements • Compliance assurance monitoring/Periodic monitoring • Qualify • Required Info. • Forms • Applicable Reqs. • CAM/PM
Initial Application Qualification • County for appropriate GOP • Qualification criteria • Preconstruction authorizations • Compliance with GOP requirements
Required Information Required Information • Process description • Process flow • Area map • Plot plan
Required Forms • Administrative Forms • Applicable Requirement Forms • Admin. Forms • Core Data Form • OP-1 • OP-CRO1 • OP-DEL (optional) • OP-SUM • Applicable Req. Forms • OP-REQ1 • OP-UA • OP-MON (optional) • OP-REQ3 (optional) • Core Data Form • OP-1 • OP-CRO1 • OP-DEL (optional) • OP-SUM • OP-ACPS • OP-REQ1 • OP-UA • OP-MON (optional) • OP-REQ3 (optional)
OP-REQ1 ATO indicator
Example Site Webb County Major source of HAPs Unit Attributes Stationary RICE (non-emergency) > 500 HP Four stroke lean burn (4 SLB) Constructed on/after 12/19/2002 REDCO - Reducing CO emissions by 93% or more Webb County Major Source of HAPS Site 4 SLB Post 12/19/2002 > 500 HP Attributes RICE (non-emerg) REDCO
Example GOP 514 Table Unit Attributes GOP Index No. Requirements > 500 hp
Example GOP 514 Table (cont.) Reducing CO emissions 4SLB 514-21-013 Requirements Normal Service Constructed On/ After 12/19/2002
Compliance Assurance Monitoring/Periodic Monitoring Compliance Assurance Monitoring (CAM) • Is in section (d) of the GOP • Has applicability criteria • May be required for standard permits or permits by rule Periodic Monitoring (PM) • In section (f) of the GOP • Has applicability criteria • May be indicated in the tables • CAM • PM • Section (d) of GOP • Section (f) of GOP • Applicability Criteria • Applicability Criteria • Standard Permits and PBRs • Indicated in Tables
Example PM Table PM Option No. Pollutant Averaging Period Indicator Monitored Periodic Monitoring Requirement Min. Freq. Both Options are Required
ATO Technical Review • Provisional terms and conditions • TCEQ reviews application • Deficiencies resolved • TCEQ issues ATO letter
Revision to ATO • Correction of typographical errors • Change, add, or remove applicability determinations • Change in name/ownership (Form) • Revision to GOP
Revision to ATO Forms Required • OP-2 • OP-CRO1 Potentially Required • OP-1 • OP-REQ1 • OP-SUMR • OP-UA • OP-MON • OP-REQ3 • OP-CRO2 • Required • OP-2 • OP-CRO1 • Potentially Required • OP-1 • OP-REQ1 • OP-SUMR • OP-UA • OP-MON • OP-REQ3 • OP-CRO2
Revision Review Policies • PBR effective dates • Scope of revision • Expected timeline of review
ATO Renewal TCEQ sends renewal notification ATO issued ATO expiration Application due (6-18 months before expiration) Five year authorization term
ATO Renewal Forms Required • OP-1 • OP-2 • OP-CRO1 • OP-ACPS • OP-REQ1 Potentially Required • OP-SUMR • OP-UA • OP-MON • OP-REQ3 • Required • OP-1 • OP-2 • OP-CRO1 • OP-ACPS • OP-REQ1 • Potentially Required • OP-SUMR • OP-UA • OP-MON • OP-REQ3
Void Requests Lowering PTE Application Area or Site Shutdown Void Request Letter PCAs Voided OP-CRO1 • Lowering PTE • Application Area or Site Shutdown • ATO Void Request Letter • APD-Cert or PI-7-Cert • ATO Void Request Letter • Request to Void PCAs • APD-CERT or • PI-7-CERT • ATO Void Request Letter
GOP Revisions and Renewals • Renewal -- every 5 years • Revision -- between renewals • Update tables and terms • Procedures • Public notice • Affected states review • EPA review • ATO responsibility
Oil and GasGOP Guidance • TexasOilandGasHelp.org • GOP Guidance • GOP Information
Submitting ATO Applications(Initial, Revisions, and Renewals) TCEQ APIRT, MC 161 P.O. Box 13087 Austin, TX 78711-3087 Copies must be mailed to the appropriate TCEQ regional office.
Submitting ATO ApplicationUpdates [Name of Assigned Permit Reviewer] TCEQ APD, MC 163 P.O. Box 13087 Austin, TX 78711-3087
Submitting ATO Application to EPA Air Permits Section (6PD-R) EPA, Region 6 1445 Ross Ave., Suite 1200 Dallas, TX 75202-2733 Submit application updates to EPA at R6AirPermits@EPA.gov. Identify the associated permit number when submitting information.
Oil and Gas GOPQuestions?Air Permits Division512-239-1250 Air Permits Division 512-239-1250