General Engineering Permits. Grading Permit Excavation or filling more than 50 cy Changing existing drainage Retaining wall that is retaining earth Within private property. Submittal Grading Permit Checklist Include amount of cubic yards (cy) Site Plan Existing elevations
E N D
Grading Permit • Excavation or filling more than 50 cy • Changing existing drainage • Retaining wall that is retaining earth • Within private property
Submittal • Grading Permit Checklist • Include amount of cubic yards (cy) • Site Plan • Existing elevations • Proposed elevations • Typical Section • Grades of slopes • Stormwater BMPs
Stormwater BMPs Chapter 2 , Figure 2-1
Stormwater Plan • Grading Plan • Drainage Plan • Snow removal and disposal • Remove contaminates before leaving site
Utility Permits • Property Line into the Structure
Water Permit • Size – Current UPC • Table 6-5 (Water Supply Fixture Units) • Table 6-6 (Fixture Unit Table) • Fees – Includes Inspections and Meter • Single Family - $750 • Commercial or Multifamily – determined by customer line size • ¾” - $750 • 1” or larger - $1,500 + $750 for each ½” over 1”, rounded up to the nearest ½” • Fire Line - $750 or the actual cost of connection
Sewer Permit • Size – Current UPC • Table 7-3 (Drainage Fixture Unit Values) • Table 7-5 (Maximum Unit Loading) • Fees – Does not include inspections • Single Family - $1,000 • Multifamily - $500 + $500 for each unit up to 4 units • Multifamily w/5 or more units or Commercial - $1,000 for the first 20 fixture units or fraction thereof and $500.00 for each additional 20 fixture units or fraction thereof
Onsite Wastewater Treatment Disposal System (OWTDS) • Requirements • Permit Fee - $100 • Service Agreement • CBJ Agreement • OR • Manufacture’s Certified Representative (MCR) Agreement
OWTDS Service Agreement • CBJ Agreement • CBJ annual inspection • CBJ pumps tank every two years • Pay current utility rate for sewer • Does not include maintenance or repair • MCR Agreement • MCR submits to CBJ annual inspection reports • MCR pumps according to manufacturer • Pays service fees and charges directly to MCR • Must be signed and submitted to General Engineering prior to TCO • New agreement needs to be signed and submitted to General Engineering at time of ownership change
Right-of-Way (ROW) Permit • Public Facility Transmission and Excavation (PFT) • Requires submittal of plan • Bonded and licensed contractor • Fees • Permit fee - $10 • Inspection - $60 per inspection • Refundable bond posted – Actual cost of work • All work must be inspected by General Engineering inspector • All inspections and conditions met and as builts if required must be submitted prior to bond return