SCHEMATIC DESIGN PRESENTATION LOCH RAVEN ELEMENTARY SCHOOL JULY 8, 2014
EXISTING BUILDING INFORMATION CONSTRUCTION HISTORY EXISTING BUILDING CONSTRUCTION 1947 CLASSROOM AND MULTI-PURPOSE ROOM ADDITION 1949 CLASSROOM ADDITION 1970 BUILDING PLACED ON BALTIMORE COUNTY HISTORIC REGISTER 2009 BUILDING SIZE 67,094 SF CURRENT BUILDING USE COMMUNITY CENTER
SITE PROJECT VICINITY MAP
PROJECT OBJECTIVES • Restore Historic Features (Interior And Exterior) of the Original 1947 Building and 1949 Multi-purpose Room Addition • Renovation and Addition to Convert Building to a New 21st Century Learning Facility • Incorporate Facility Upgrades to Support The Instructional Environment for Students • Provide All New Building Systems • Provide Building Security and Address Student Safety • Address all Code, ADA and Life Safety Issues
RESIDENTIAL LOCH RAVEN ELEMENTARY SCHOOL SHOPPING CENTER LIBRARY / HEALTH CENTER SITE CONTEXT 200’ 400’
EXISTING LOWER LEVEL PLAN EXISTING UPPER LEVEL PLAN
BALL FIELDS PAVED PLAY MULTIPURPOSE FIELD PARKING KINDER PLAY BUS DROP-OFF SWM PROPOSED SITE PLAN 200’ 400’
PROPOSED LOWER LEVEL PLAN PROPOSED UPPER LEVEL PLAN
PROPOSED BUILDING INFORMATION • State rated capacity (SRC) 610 students • Proposed building area 102,108 SF • Project scope Renovation and addition • SUMMARY OF IMPROVEMENTS: • CURRICULUM • The building interior will be designed to new curriculum and building standards and will meet BCPS and Maryland’s Standard for Technology • BUILDING ENVELOPE • Roof replacement • Repair /restore existing building envelope and improve thermal value • CODE IMPROVEMENTS • Install elevator(s) to access all levels • Provide code compliant restrooms and stairs • Provide code compliant hardware and doors • MEP SYSTEM IMPROVEMENTS • New mechanical, electrical and plumbing systems to be provided • Fire protection, telecommunications and security systems to be provided • Upgrades to incoming utilities
VIEW OF NEW ENTRANCE VIEW OF NEW ENTRANCE PERSPECTIVE VIEWS OF NEW ENTRANCE
VIEW OF ADMINISTRATION WING AND GYMNASIUM VIEW OF KINDERGARTEN ADDITION PERSPECTIVE VIEWS OF THE SOUTHERN FACADE
NORTH ELEVATION WEST ELEVATION
PROJECT SCHEDULE DESIGN March 2014 – January 2015 BIDDING AND PROCUREMENT January 2015 – April 2015 CONSTRUCTION May 2015 – July 2016 OCCUPANCY August 2016