1 / 16

The Nature of Risky Futures

The Nature of Risky Futures. Michael Schilmoeller Thursday May 19, 2011 SAAC. Outline. Return to Future 750 Overbuilding, is it expensive? “Overbuilding is a planning blunder” Lack of foresight and the consequences The role of mid-study CCCTs Getting it wrong. Future 750.

eshe
Download Presentation

The Nature of Risky Futures

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Nature of Risky Futures Michael Schilmoeller Thursday May 19, 2011 SAAC

  2. Outline • Return to Future 750 • Overbuilding, is it expensive? “Overbuilding is a planning blunder” • Lack of foresight and the consequences • The role of mid-study CCCTs • Getting it wrong

  3. Future 750 NPV Cost: $72,351,242,187.50 C:\Backup\Plan 5\Portfolio Work\Olivia\SAAC 2010\110519 SAAC Meeting\Analysis of futures\Illustrations\Spinner_L813LR_EUCI_SAAC.xls

  4. Average over all futures NPV Cost: $78,868,493,989.58

  5. Loads

  6. Electricity Price

  7. Natural Gas Price

  8. Carbon Penalty

  9. Power Cost per kWh

  10. A More Useful Comparison • Compare Future 750 with CCCTs against Future 750 without CCCTs • Look not only at cost, but also at what the cost burden per ratepayer would be • Use (Total Cost)/(Frozen Efficiency Load), not (Total Cost)/(Frozen Efficiency Load-Conservation Energy) • We want to treat conservation as we would any other resource used to meet the frozen efficiency load

  11. Future 750 with no CCCT NPV Cost: $72,351,242,187.50 NPV Cost: $66,913,822,724.86 Source: C:\Backup\Plan 5\Portfolio Work\Olivia\SAAC 2010\110519 SAAC Meeting\Analysis of futures\L8133Future_750_110429_150342 no CCCT.xls

  12. Future 750 with no CCCT

  13. We Need To Get It Wrong Sometimes • How much we are willing to pay for an option (to build a power plant) depends on both • The cost if we cannot build it, but turn out to need it • The cost if we build it, but turn out not to need it

  14. The Value of Mid-Study CCCTs • The Sixth Power Plan resource portfolio included siting and licensing for nine 415 MW CCCTs, such that we could break ground in 2019 • Expected load growth was virtually flat and electricity and natural gas prices were moderate • The plan did not “predict” we would build the CCCTs; probability of completion was about 30 percent. • The preparation for the CCCTs was driven by the carbon penalty risk

  15. End

  16. Source: workbook “L811x1_LR2.xls”, worksheet “Data (9)”

More Related