1 / 11

CRITICAL PATH ANALYSIS MAY 2011 PAPER

CRITICAL PATH ANALYSIS MAY 2011 PAPER. DETAILED STEP BY STEP ANSWER GUIDE. Calculating the total project time. Activity A Is an independent event. It takes 2 weeks. Activity B Must follow A. 2 + 2 = 4 weeks Activity C Must follow B. 4 + 5 = 9 weeks. Activity D Must follow B

esme
Download Presentation

CRITICAL PATH ANALYSIS MAY 2011 PAPER

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CRITICAL PATH ANALYSISMAY 2011 PAPER DETAILED STEP BY STEP ANSWER GUIDE

  2. Calculating the total project time Activity A • Is an independent event. • It takes 2 weeks. Activity B • Must follow A. • 2 + 2 = 4 weeks Activity C • Must follow B. • 4 + 5 = 9 weeks. Activity D • Must follow B • 4 + 7 = 11 weeks

  3. Calculating the total project time CRITICAL PATH CHECK Activity E • Must follow C. • 9 + 4 = 13 weeks. Activity F • Must follow D. • 11 + 3 = 14 weeks. Activity G • Must follow E & F. • F is the longest. • So. 14 + 3 = 17 weeks.

  4. Calculating the total project time Activity H • must follow G. • 17 weeks + 2 = 19 weeks. Activity I • 19 weeks + 5 = 24 weeks. Critical Path Check Relationship between Activity I & Activity H Total Activity 1 = 24 Minus (duration) 5 = 19 weeks Activity H is critical

  5. What does 24 represent? • 24 represents the total project time. • It will be the final node in our network. • It will be the 9th activity & therefore 9th node. • Therefore our last node will look like: 24 24 9

  6. How do I work out the critical path?How do I work at the non-critical paths? • What activities must happen to reach node 9 (24 weeks) • We can identify the critical path by subtracting the duration from each activity, to see if it equals the previous activity. • The table on the next page summarizes the relationships.

  7. Is there a missing node in our diagram? • On the answer sheet, you will notice there appears to be an activity node missing • The node that appears missing is Activity E. • To understand, why this is the case, you must look at Activity G. Activity G is dependent on E & F. • As a general rule, whenever, the following event is dependent on two previous events, the two activities will be combined into one node. • Whatever, is the largest number will dominate. • Thus F, is clearly larger than E & being the critical path will dominate. • Therefore activity E, is actually not represented by itself.

  8. Calculating the Total FloatQii Calculate the total float on the network diagram & common ton its implications for New World What is the total float? This is the amount of a time a sequence of tasks can be delayed without having an impact on the whole process.

  9. Critical Paths & Total Floats Very Important: Critical Path & Float • All activities on the critical path have 0 floats and there is no need for calculations. • Therefore only activities C & D, require a float calculation.

  10. How do I calculate the total float? Formula for Calculating the Total Float • LFT of the current activity (minus -) duration of the current activity (minus -) EST of the previous activity Activity C 10 – 5 – 4 = 1 week Activity E 14-4-9 = 1 week

More Related