Anode Power Supply Update. 8/20/2014 Ryan Crawford. Schedule. Enclosure. 4 weeks behind schedule Panel issues ( b ad paint, bent) Promise to ship by 9/12. Diode Bridge. 14 bare sticks built up Waiting on PCB to complete all 14 legs 36 required for 2 supplies and 1 complete spare
E N D
Anode Power Supply Update 8/20/2014 Ryan Crawford
Enclosure • 4 weeks behind schedule • Panel issues (bad paint, bent) • Promise to ship by 9/12
Diode Bridge • 14 bare sticks built up • Waiting on PCB to complete all 14 legs • 36 required for 2 supplies and 1 complete spare • PCB should arrive by 9/5 • All diodes are on site • All spacers are on site
Capacitors • 38 capacitors on site, 40 ordered • One frame is nearing completion
Misc. • All PTs on site • Heat exchangers on site • Buss bar has issues • May cause slight delay • May have enough good pieces to finish one supply • We will know once the other two skids arrive • Working on water cooled resistor • Original design was scraped due to longevity concerns • Redesigning with flanged fiberglass tube • Looking into commercially available option