An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BRIDGES ON THE MOVE Sean Poynter, LEED-AP Senior ABC Estimator

  2. A LITTLE ABOUT SARENS…

  3. BRIDGES ON THE MOVE… FIRST BRIDGE MOVE COMPLETED IN 1980 SINCE THEN WE COMPLETE ON AVERAGE 70 BRIDGES EVERY YEAR BRIDGE MOVES VARY FROM CONCRETE DECK ON STEEL, CONCRETE DECK ON CONCRETE GIRDERS, STEEL TRUSS BRIDGES, ETC. HEAVIEST BRIDGE MOVED IN U.S.- SAM WHITE BRIDGE IN LEHI, UT 354 FEEL LONG AND WEIGHING 4,200 KIPS

  4. SELF-PROPELLED MODULAR TRANSPORTERS (SPMT’s) • USUALLY SEE 4 KINDS OF SPMT’S USED IN THE US. • KAMAG (SARENS CHOICE) • GOLDHOFER • SCHEURLE • NICOLAS

  5. WHAT THE DESIGNER SHOULD KEEP IN MIND • SPMTS (KAMAG) COME IN CONFIGURATIONS OF 4 AND 6 AXLES. • EACH AXLE HAS A MAXIMUM CAPACITY OF ROUGHLY 79 KIPS • MUST CONSIDER SUPPORT STRUCTURE WHEN DETERMINING SPMT QUANTITY (WEIGHT). • SPACE CONFINEMENTS…..DO THE SPMT’S WORK WITH THE SPACE PROVIDED. • GROUND BEARING CONCERNS.

  6. SPMT BENFITS INCLUDE: COUPLING SIDE BY SIDE OR END ON END. FLEXIBLE STEERING. ACCURATE ALIGNMENT. CENTRAL CONTROL UNIT. DIAGONAL/CRAB DRIVE FROM 0°TO 110° CIRCLE DRIVE “CAROUSEL” AROUND THE CENTER OF THE CONFIGURATION.

  7. WHY SPMT’s OR ABC REDUCE USER COST ALLOW BRIDGE ERECTOR TO BUILD OFF SITE AND OUT OF TRAFFIC. MINIMIZE TRAFFIC IMPACT. FASTER COMPLETION TIME. INCLEMENT WEATHER HAS LESS IMPACT ON CONSTRUCTION SCHEDULE. GOOD INVESTMENT EVERY $1 SPENT ON ABC THER IS A $5 SAVINGS ON USER COSTS.

  8. HOW SARENS MOVES BRIDGES SUPPORT BEAMS CROSS-BRACING FOR LATERAL SUPPORT 610mm SUPPORT SPOOLS 12-AXLE LINES

  9. EXAMPLE PROJECTS: ABERDEEN AVENUE – HAMILTON, ONTARIO SAM WHITE – LEHI, UT WELLESLEY – WELLESLEY, MA TORRENCE AVENUE – CHICAGO, IL

  10. ABERDEEN AVENUE EXAMPLE PROJECTS LOCATION: HAMILTON, ON MAJOR THOROUGHFARE: HIGHWAY 403. JOB: REMOVE TWO (2) EXISITING SIMPLE SPANS AND REPLACE WITH TWO (2) NEW SPANS. WEIGHT: ~1,200 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 12 HOURS

  11. SAM WHITE EXAMPLE PROJECTS LOCATION: LEHI, MA MAJOR THOROUGHFARE: I-15. JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~4,200 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 12 HOURS EQUIPMENT: 96-AXLE LINES KAMAG SPMT’s

  12. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s ABUTMENT PREPARATION

  13. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s ROLLING OUR FROM TEMPORARY CONSTRUCTION ABUTMENTS

  14. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s ROLLING OUT

  15. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s USE OF CS250 FOR ADDITIONAL JACKING CAPABILITIES

  16. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s OPERATION OF THE SPMT’s

  17. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s AXLES ROTATED TO CRAB

  18. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s KEEPING THE DECK LEVEL ON UN-LEVEL TERRAIN

  19. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s PROJECT ENGINNER MONITORING DEFLECTION

  20. WELLESLY EXAMPLE PROJECTS LOCATION: WELLESLEY, MA MAJOR THOROUGHFARE: STATE HIGHWAY 9 JOB: SET ONE (1) TWO-SPAN BRIDGE SECTION. WEIGHT: ~1,000 KIP CONSTRUCTION: STEEL GIRDER WITH CONCRETE DECK. TIMELINE: 6 HOURS EQUIPMENT: 24-AXLE LINES KAMAG SPMT’s SETTING THE BRIDGE!

  21. TORRENCE AVE. EXAMPLE PROJECTS LOCATION: CHICAGO, IL MAJOR THOROUGHFARE: CHICAGO COMMUTER TRANSIT JOB: SET ONE STEEL TRUSS BRIDGE WEIGHT: ~4,400 KIP CONSTRUCTION: STEEL. TIMELINE: 6 HOURS EQUIPMENT: 96-AXLE LINES KAMAG SPMT’s

  22. THE END THANK YOU