1 / 5

ERCOT Transmission Protections System Misoperations Data 138kV and 345kV Combined

This report analyzes the transmission operator protection system misoperations in the ERCOT system from 2011 to 2014. It highlights human performance issues and provides trends and corrective actions.

eustice
Download Presentation

ERCOT Transmission Protections System Misoperations Data 138kV and 345kV Combined

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT Transmission Protections System Misoperations Data – 138kV and 345kV Combined (Not including Failure to Reclose) Transmission Operator Protection System Misoperations2014 NOTE: Includes only transmission system protection system misoperations from 1/1/2011 thru 6/30/2014 reported by Transmission Operators

  2. Protection System Misoperations 2014 Q2

  3. Protection System Misoperations 2014 Q2 Summary of Human Performance Issues noted for 2014 Q2: 138 kV line overtrip during substation re-configuration project. New relay settings were installed on the line terminal but the carrier frequency was not changed to reflect the new substation configuration. 138 kV line overtrip occurred with MDAR relay set to zero polarization on one terminal and SEL321 with negative sequence polarization on the other terminal. Multiple 345 kV lines overtripped due to a failed CT on a short line between a substation and a generation plant. Remote line terminals tripped due to miscoordination between the backup ground relays and the remote bus ground backup directional overcurrent relays. Misoperation of 345 kV auto due to wind blowing the cabinet door, causing the SPR auxiliary relay to vibrate and trip. 138 kV line overtrip due to incorrect line length in Aspen model. 138 kV bus differential failed to trip for a fault due to incorrect wiring from the CTs to the relay.

  4. Protection System “Human Performance” Trends “Human” performance misoperations defined as the percentage of misoperation each quarter caused by incorrect settings, incorrect design, logic errors, and as-left personnel errors.

  5. Protection System Corrective Action Trends

More Related