Commercial Operations Sub-Committee Update to TAC December 4, 2008. Highlights from November 11 th Meeting. Discussed problem with initial settlement of EILS payment : 1 st EILS period ending May 31 st settled using “Initials” for applying Load Ratio Shares of EILS cost.
E N D
Commercial Operations Sub-Committee Update to TAC December 4, 2008
Highlights from November 11th Meeting • Discussed problem with initial settlement of EILS payment: • 1st EILS period ending May 31st settled using “Initials” for applying Load Ratio Shares of EILS cost. • ERCOT Staff and COPS suggest changes (new PRR) be crafted to correct this problem. • ERCOT noted 2nd EILS period ending Sept. 30th will use Final (R4’s) for applying LR Share of costs. • 3rd Period to incorporate Final and True-up statements in determining LRS of EILS costs. • DEWG/SDAWG to work with ERCOT Staff and submit new PRR to correct problem. • Update from ERCOT regarding recent mismatched schedules: • ERCOT noted this is an IT issue and staff is working to determine cause and corrective process to resolve issue.
DEWG / SDAWG Worked with ERCOT to resolve EILS Settlement Issue: PRR786, submitted to target ERCOT to use the most recent Load Ratio Share (Final Settlement Version) and so a resettlement using the most current load (True-up Settlement Version) Normal report on ERCOT issues: Slight decline in number of issues, most recently centered around Lodestar Upgrade, though no major issues. Followed up on the ERCOT stabilization efforts: Identified projects to watch for in 2009 that address common flaws in the current systems around reports and extracts that need to be maintained until Nodal replacement is implemented.
CCWG • CCWG met on 11-18-08 • Developed wish list of improvements for the “ERCOT.com” website to assist ERCOT in understanding website satisfaction survey indicators. • Reviewed draft of new Renewable Energy Credit Section of COPMG. • Continue to work on other sections of the COPMG in anticipation of Nodal.
PWG LPGRR032 – Profile Decision Tree Changes for Advanced Meters was recommended unanimously IA to be reviewed at next PWG meeting (12/18/08) Working on Draft PRRs for Section 18 Protocols: To remove “grey boxes” for unfunded project # PIP106 linked to PRR385 and PRR478 for DLC. Clarify language on procedure if a Hurricane or other natural disaster like IKE causes delay in completion of Annual Validation of Profile Id Assignments. On schedule: Annual Validation process, Round 2 Load Research data for recalibration of current load profiles (December 2010) 2009 PWG goals developed to present to COPS at 12/08/08 meeting.
TAC Assignment – Market Participant Survey • Dispute Resolution: • COPS agrees with ERCOT Action Plan • Suggests that MPs need to better understand dispute process • Review ADR process – Survey results most likely the result of ADR issues • Format of Settlement Statements: • Statements remain unchanged since last survey – COPS unsure as to reason for change from last survey • COPS agrees with ERCOT Action Plan and suggest MPs will now have to shadow from extracts upon implementation of Nodal. • Data Extracts and Reports: • COPS agrees with ERCOT Action Plan & agrees new Extract SLA will improve awareness and understanding of Extract and Report Expectations. • Website Satisfaction: • CCWG agrees with ERCOT action plan & has developed a list of improvements for the “ERCOT.com” website to assist ERCOT in understanding website satisfaction survey indicators.