Preliminary Agreements in Tendering

Preliminary Agreements in Tendering. Stanislav Roth www.sourcelegal.com.au . Focus for today. Overview of contract formation Law on preliminary agreements Pre-bid and early works agreements in tendering. Innovative legal outsourcing solutions. Contract formation.

fawzia
Download Presentation

Preliminary Agreements in Tendering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Preliminary Agreements in Tendering Stanislav Roth www.sourcelegal.com.au

  2. Focus for today • Overview of contract formation • Law on preliminary agreements • Pre-bid and early works agreements in tendering www.sourcelegal.com.au Innovative legaloutsourcing solutions

  3. Contract formation www.sourcelegal.com.au

  4. What is a preliminary agreement? • Memorandum of understanding • Heads of agreement • Letter of intent • Pre-bid agreement • Teaming agreement • Early works agreement www.sourcelegal.com.au

  5. Law on preliminary agreements Three categories - Masters v Cameron (1954) 91 CLR 353 • Parties agree on all terms but propose to have them restated in more detail in a formal contract (binding) • Parties agree on all terms but have made performance of some of them conditional upon the execution of a formal contract (binding) • Parties do not intend to be bound unless and until they execute a formal contract (non-binding) www.sourcelegal.com.au

  6. Law on preliminary agreements ! But important fourth category: • Parties intend to be bound by the terms agreed while expecting a further formal contract in substitution of the first and containing further terms (binding) www.sourcelegal.com.au

  7. To bind or not to bind? • “Subject to contract” – not decisive but indicative of “non-binding” • Terminology (LOI, MOU, HOA…) - not decisive • Objective construction of the language and context (pre- and post-agreement communications are relevant) www.sourcelegal.com.au

  8. Pre-bid agreements • Useful tool for early partnering • May enhance tendering capabilities/credibility • Typical issues: • Binding or non-binding • Exclusive or non-exclusive • Future contractual structure: • Subcontract (back-to-back terms with head contract?) • Joint venture/consortium (beware of the Competition and Consumer Act). If JV, “joint and several” liability to customer is likely - need to consider how liability is apportioned between JV partners • Exit provisions, division of scope, key terms of future contract (e.g. limitation of liability) www.sourcelegal.com.au

  9. Early works agreements • Convenient for tight schedule projects – early engineering, long lead delivery equipment • May give contractor/supplier leverage • Typical issues: • Binding or non-binding • Scope of work under EWA • Payment for work under EWA • Applicable terms of contract • Timeframe for entering into future contract • Termination/exit and applicable payment www.sourcelegal.com.au

  10. What’s the matter with preliminary agreements? • Often not clear whether binding or not • If binding: • often incomplete/poorly drafted • leave many important matters to future agreement • fail to have appropriate exit provisions • risk of parties failing to follow through with a proper agreement • If non-binding: • why do it? • work is performed without contract - unlimited liability, no contractual warranties etc • no certainty of recouping start-up or project cancellation costs www.sourcelegal.com.au

  11. Checklist • Use preliminary agreements selectively. Avoid unnecessary preliminary agreements. • Use clear words to indicate whether a preliminary agreement should be binding or non-binding. Draft the preliminary agreement accordingly. • Avoid templates. Every preliminary agreement is specific to the needs of the project. • Clearly define what the parties are to do in accordance with the preliminary agreement. • Provide for a framework and timetable for entering into a formal contract and cover any key terms. • Outline what should happen if such contract does not eventuate. www.sourcelegal.com.au