Meyrin Accelerator Cooling. Scott Campbell ST-MO-TC. Topics. Installations connected with synoptic representation Installations connected without synoptic representation Installations not connected Known current problems Cooling Station Process Control Upgrade(COSPCU) Project
E N D
Meyrin Accelerator Cooling Scott Campbell ST-MO-TC
Topics • Installations connected with synoptic representation • Installations connected without synoptic representation • Installations not connected • Known current problems • Cooling Station Process Control Upgrade(COSPCU) Project • Future TCR - CV Collaboration
Known Current Problems In The PS • After the power cut of the 7th June, data in the API215 was lost, the station was restarted before the previous data was installed. The Station has to be stopped to re-install. Hence the experiment has to be stopped.
COSPCU Project • The project launch sheet includes: Installations that currently have attributed synoptics, plus the Demineralised Stations of West Zone, Main Magnet, SW18; the Chilled Water Stations 355 and 513. It however does not include Building 378 and the TOF installation.
Installations At 378 • Primary Water supplying the Chilled and Demineralised water in this building. • Demineralised water supply TOF, ISR, Partially the Transfer Tunnel and the West Zone. • Chilled Water for ISR and West Zone. • Only one alarm connected: General Grouped Fault ST/CV equipment
Future • For the near future, the installations that are not connected should be at least connected with a hardwire alarm. • The work required by ST/CV in the PS and the TCR in the next year is very heavy, after which the TCR will be able to give a complete service to the CPS installations in collaboration with the CV-PS team.