An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMERGENCY CONTRACTING AND HURRICANE KATRINA Thomas H. Gourlay, Jr. Chief Trial Attorney U.S. Army Corps of Engineers

  2. Themes • Authorities • Application • The “New Paradigm”

  3. Authorities • Stafford Act (Disaster Relief Act of 1974), P.L. 93-288, 42 U.S.C. §5121 • Flood and Coastal Storm Emergencies Act, P. L. 84-99, 33 U.S.C. §701n

  4. Stafford Act • Four bases for invocation • “Major Disaster”: Presidential declaration of any natural catastrophe, with Governor input • “Emergency”: Supplement to state efforts; limited to $5 million • “Interim” Assistance: Work in immediate aftermath; work only authorized for 10 days • “Exclusive Responsibility”: Federal Government exercises exclusive or preeminent responsibility

  5. Stafford Act Coverage • USACE mission: Public Works & Engineering (ESF#3) • Debris removal • Construct temporary emergency access routes • Emergency restoration of public services/utilities • Emergency demolition/stabilization of damaged structures • Technical assistance & damage assessment • Administered by FEMA; funding levels established through negotiations • Work performed under the auspices of the Economy Act (31 U.S.C. §1535)

  6. Flood and Coastal Storm Emergencies Act • Establishes emergency fund for the following: • Disaster preparedness (any natural disaster) • Emergency Operations (flood-fighting/rescue operations) • Rehabilitation of flood control and hurricane protection structures • Emergency Water Supplies & Drought Assistance • Advance Measures • Used when preparation measures are beyond capability of local interests and State to perform in a timely manner

  7. Application: AshBritt, Inc.,B-297889; B-297889.2 • AshBritt had Advance Contract Initiative contract (ACI) • Pre-placed contract • Maximum capacity - $500 million • USACE determined that this instrument was inadequate in light of the magnitude of the disaster; capacity would be exhausted before completion of mission

  8. AshBritt, Inc. (cont). • Acquisition Plan for additional demolition and debris removal. Capacity - $300 million • Competition limited to firms residing or doing business primarily in Mississippi • Solicitation included 8 non-exclusive factors for geographic eligibility • State of incorporation; MS permanent office • MS licenses; membership in state organizations • Past work in MS; % of gross revenues attributable to MS work • Permanent employees in MS • Three contracts – each contract would be confined to designated counties • Unrestricted on business size • HubZone firms • 8(a) firms • Objectives: structural demolition, debris removal & site clean-up • 6,000 structures • 2.1 million cubic yards of material

  9. AshBritt, Inc., (cont). • AshBritt Protested proposed acquisition • Bases included: • Solicitation violated CICA and the Stafford Act • Agency issued Solicitation in response to political pressure • Stafford Act and FAR implementation ambiguous • Guidance on what constitutes a firm residing/primarily doing business in MS defective, inconsistent, arbitrary, unreasonable & irrational

  10. CICA and the Stafford Act • CICA mandates full and open competitive procedures, with seven exceptions. The fifth exception applies when “authorized or required by statute.” • Stafford Act provides that “preference shall be given, to the extent feasible and practicable to [firms] residing or doing business primarily in the area affected” by the disaster. 42 U.S.C. §5150. • Legislative history – “One outstanding feature of the aftermath of a great disaster is lack of ready cash. A Federal assistance program should be designed to revitalize the community by infusions of cash through the use of local people and business firms.” • FAR §6.302-5(a)(5), “Authorized or required by statute,” specifically invokes Stafford Act.

  11. Set-Asides and the Stafford Act • HAP Construction, Inc., B-280044.2, 98-2 CPD ¶76 • USACE contract for debris removal and related services in Puerto Rico and USVI after storm • Agency used local contractor evaluation preference, as opposed to local firm set-aside • GAO will not disturb Agency’s implementation of statutory procurement unless inconsistent with Congressional intent

  12. The “New Paradigm” • Traditional Congressional interest/oversight • Constituent service • Oversight • Post-Iraq and Katrina climate • Potential impact on relationship between contractors and Government