1 / 25

REGIONAL PLANNING PROJECT MEETING JULY 9, 2008

230 kV LINE WALLA WALLA – WALLULA – Mc NARY 500 kV LINE HEMINGWAY – CAPTAIN JACK – REGIONAL PLANNING MEETING. REGIONAL PLANNING PROJECT MEETING JULY 9, 2008.

fherring
Download Presentation

REGIONAL PLANNING PROJECT MEETING JULY 9, 2008

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY500 kV LINE HEMINGWAY – CAPTAIN JACK – REGIONAL PLANNING MEETING REGIONAL PLANNING PROJECT MEETING JULY 9, 2008

  2. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY500 kV LINE HEMINGWAY – CAPTAIN JACK – REGIONAL PLANNING AND PROJECT RATING PROCESS

  3. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY500 kV LINE HEMINGWAY – CAPTAIN JACK - PROJECT GUIDELINES 1. Take multiple project needs and plans into account, including identified utilities’ and non-utilities’ future needs, environmental and other stakeholder interests; 2. Cooperate with others to look beyond specific end points of the sponsors’ project to identify broader regional and subregional needs or opportunities: 3. Address the efficient use of transmission corridors (e.g., right-of-ways, new projects, optimal line voltage, upgrades, etc.);

  4. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY500 kV LINE HEMINGWAY – CAPTAIN JACK - PROJECT GUIDELINES 4. Identify and show how the project improves efficient use of, or impacts existing and planned resources of the region (e.g., benefits and impacts, transmission constraint mitigation); 5. Cooperate with Regional Planning Review Group members in determining the benefits and impacts due to the project; 6. Identify transmission physical and operational constraints resulting from the project or that are removed by the project;

  5. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY500 kV LINE HEMINGWAY – CAPTAIN JACK - PROJECT GUIDELINES 7. Coordinate project plans with and seek input from all interested members, subregional planning groups, power pools, and region-wide planning group(s); 8. Coordinate project plans with and seek input from other stakeholders including utilities, independent power producers, environmental and land use groups, regulators, and other stakeholders that may have an interest; 9. Review the possibility of using the existing system, upgrades or reasonable alternatives to the project to meet the need (including non-transmission alternatives where appropriate);

  6. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY500 kV LINE HEMINGWAY – CAPTAIN JACK - PROJECT GUIDELINES 10. Indicate that the sponsor’s evaluation of the project has taken into account costs and benefits of the project compared with reasonable alternatives; 11. Coordinate with potentially parallel or competing projects and consolidate projects where practicable.

  7. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY500 kV LINE HEMINGWAY – CAPTAIN JACK – STUDY AREA

  8. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY 230 kV LINE WALLA WALLA – WALLULA – Mc NARY • PROJECT • BENEFITS • ALTERNATIVES STUDIED

  9. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY PROJECT • CONSTRUCT NEW SINGLE-CIRCUIT 230 kV LINE FROM WALLA WALLA TO WALLULA TO Mc NARY • APPROXIMATELY 56 MILES OF NEW LINE • LINE TERMINALS REQUIRED AT WALLA WALLA, WALLULA AND Mc NARY • PROPOSED IN-SERVICE DATE IS 2010.

  10. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY BENEFITS • PROVIDES UP TO 400 MW OF NEW TRANSMISSION CAPACITY • IMPROVES TRANSMISSION RELIABILITY • PROVIDES TRANSMISSION CAPACITY FOR NEW WIND RESOURCES • FACILITATES FUTURE INTERCONNECTION OF OTHER REGIONAL TRANSMISSION PROJECTS

  11. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY

  12. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY – SYSTEM BEFORE REINFORCEMENTS (POTENTIAL WIND ON)

  13. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY- SYSTEM AFTER REINFORCEMENTS

  14. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY– SYSTEM AFTER POTENTIAL DOUBLE CIRCUIT OUTAGE

  15. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY CONCLUSIONS TO-DATE • Single Circuit performs well • Double Circuit performs better • Present needs indicate a double circuit is not required • RAS needed for higher wind penetrations • New corridor for line will be difficult to obtain

  16. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY NEXT STEPS • ADDRESS REGIONAL PLANNING GUIDELINES • PREPARE REGIONAL PLANNING PROJECT REPORT • INITIATE PHASE 1 RATING PROCESS

  17. 230 kV LINE WALLA WALLA – WALLULA – Mc NARY COMMENTS/QUESTIONS?

  18. 500 kV LINE HEMINGWAY – CAPTAIN JACK 500 kV LINE HEMINGWAY – CAPTAIN JACK • PROJECT • BENEFITS • ALTERNATIVES STUDIED

  19. 500 kV LINE HEMINGWAY – CAPTAIN JACK PROJECT • 320 MILE (APPROX.) SINGLE CIRCUIT 500 kV LINE FROM NEW PROPOSED HEMINGWAY SUBSTATION NEAR MELBA, IDAHO TO THE EXISTING CAPTAIN JACK 500 kV SUBSTATION IN SOUTHERN OREGON. • PROPOSED IN-SERVICE DATE IS 2014.

  20. 500 kV LINE HEMINGWAY – CAPTAIN JACK ALTERNATIVES STUDIED • USED WECC 2010 LIGHT AUTUMN CASE • ADDED TO BASE CASE: • GATEWAY CENTRAL, WEST & SOUTH • I-5 REINFORCEMENT • NORTHERN CALIFORNIA LINE • SOUTHERN CROSSING • WEST OF Mc NARY • EVALUATED POWER SYSTEM SENSITIVITY TO HVDC TERMINUS • EVALUATED POWER SYSTEM SENSITIVITY TO HEMINGWAY TO CAPTAIN JACK TERMINUS

  21. 500 kV LINE HEMINGWAY – CAPTAIN JACK BENEFITS • SUPPORT WEST SIDE LOAD GROWTH • ADDRESS RENEWABLE PORTFOLIO STANDARDS • FACILITATES FUTURE INTERCONNECTION OF OTHER REGIONAL TRANSMISSION PROJECTS

  22. 500 kV LINE HEMINGWAY – CAPTAIN JACK

  23. 500 kV LINE HEMINGWAY – CAPTAIN JACK - ALTERNATIVE A - HVDC TERMINAL ADJACENT TO GRIZZLY 500 kV

  24. 500 kV LINE HEMINGWAY – CAPTAIN JACK NEXT STEPS • ADDRESS REGIONAL PLANNING GUIDELINES • PREPARE REGIONAL PLANNING PROJECT REPORT • INITIATE PHASE 1 RATING PROCESS

  25. 500 kV LINE HEMINGWAY – CAPTAIN JACK COMMENTS/QUESTIONS?

More Related