Cost Algorithm for a Super-B Factory

Cost Algorithm for a Super-B Factory. John T. Seeman SBF Workshop SLAC June 15, 2006. Prices. Costs are approximate and can change easily. Oku-yen ~ MEuro ~ M$ Different geometries have very different estimates. Linear-B scheme. HER injection. LER injection. LER. HER.

finley
Download Presentation

Cost Algorithm for a Super-B Factory

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost Algorithm for aSuper-B Factory John T. Seeman SBF Workshop SLAC June 15, 2006

  2. Prices • Costs are approximate and can change easily. • Oku-yen ~ MEuro ~ M$ • Different geometries have very different estimates.

  3. Linear-B scheme HER injection LER injection LER HER LER Bunch compressor and FF HER Bunch compressor and FF IP Overall ring length about 6Km, Collision frequency about 120Hz*10000bunch_trains=1.200MHz Bunch train stays in the rings for 8.3msec, then is extracted, compressed and focused. After the collision the bunch is reinjected in its ring

  4. 1.5 GeV Linac 2 GeV Linac 1.5 GeV Linac Damping Rings 2 GeV e- Gun e+ Gun Linac Linac Linear Super B schemes with accelerationand energy recovery, to reduce power 2 GeV e+ injection 4 GeV e- • Use SC linacs to recover energy • Use lower energy damping rings to reduce synchrotron radiation • No electron damping ring • Make electrons fresh every cycle • Damping time means time to radiate all energy • Why not make a fresh beam if storage time is greater than 1 damping time 2GeV e+ DR e- Gun IP 5GeV e+ SC Linac 4GeV e- SC Linac 7GeV e+ e- Dump

  5. Simplified layout in the Small Disruption Regime Collisions every Turn P. Raimondi ILC ring with ILC FF ILC Compressor, 0.4GeV S-Band or 1GeV L-Band Crossing angle optional Decompressor Decompressor FF FF IP Compressor Compressor

  6. Simplified layout in the Small Disruption Regime Collisions every turn Uncompressed bunches Crossing angle = 2*25 mrad Crabbed Y-Waist ILC ring & ILC FF P. Raimondi FF FF IP

  7. SBF projected cost in 2004 for 15 A on 8 A.

  8. K. Oide at CERN Meeting May 2006

  9. SuperKEKB (May 2006) • RF 105 M$ • Vacuum 112 M$ • Magnet 19 M$ • Linac 49M$ • Damping Ring 15 M$ • IR 7 M$ • Beam Monitor 15$ • Intrastructure 76 M$ • Beam transport 2 M$ • Control 6 M$ • Crab cavities 14 M$ • Total 420 M$

  10. SuperKEKB: June 2006 Oku-yen Funakoshi

  11. Draft: top down cost estimate without specific engineering knowledge This is for illustration only and not an official cost estimate.