CITY OF CANYONVILLEDOUGLAS COUNTY, OREGONPREDESIGN MEETINGJUNE 27, 2012
SITE PLANS PROCESS DIAGRAMS MECHANICAL – HEADWORKS AND PUMP STATION COST ESTIMATES SCHEDULE QUESTIONS / COMMENTS PRESENTATION OUTLINE
SITE PLANS • PHASE I & II SITE PLAN • PHASE I SITE PLAN
PROCESS DIAGRAMS • GENERAL PROCESS DIAGRAM • HEADWORKS • INFLUENT PUMP STATION • ALUM FEED SYSTEM • DECHLORINATION SYSTEM • EFFLUENT DISPOSAL
SCHEDULE JULY 2012 DEQ APPROVAL OF PRE-DESIGN REPORT AUGUST 2012 SUBMIT ENVIRONMENTAL REPORT SEPTEMBER 2012 PLAN REVIEW MEETING OCTOBER 2012 DEQ APPROVAL OF PLANS ALSO: • SEISMIC ANALYSIS (PINNACLE) EXIST’G TREATMENT UNIT • PHASE II VALUE ENGINEERING AFTER PHASE I DESIGN • ONE-STOP MEETING | IFA,DEQ,USDA-RD