An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project SMACC Twelfth report[20 min]18/10/2013

  2. Activities since last LSC (27/09/2013) • Arc splices installation • By Activities • By sectors • Globally • SIT • DFBA • DN200 • Dashboards • Activities for the next 2 weeks • Conclusions

  3. SMACC Main activities for the next 2 weeks 3 From last LSC (27.09.2013) • Sector 56 : • Work on non-conformities including repair of overheated cable • Reclosure (not in priority) and final leak test • Sector 67 (Priority sector) • Complete installation of insulation boxes and injection • Rewelding of M sleeves • Leak test of M lines • Reclosure of interconnections and final leak tests • DFBA consolidation • Sector 78 • Installation of shunts – start installation of electricalinsulation • Quadrupole diodes consolidation • DFBAs consolidation • Reconnection of Q5L8 • Sector 81 • Complete ElQC of existingsplices • Desoldering / Resoldering of splices • Installation of shunts • Other sectors: • S12: Start ElQC of existingsplices • S23: Open busbarlines and diodes containers • S34 & 45: Reconnection of replacingmagnets • Advanced opening for outliers and CSCM segments • Inspection of connection cryostats  Overheated splice redone, ≈120 ICs reclosed, 3 subsectors validated, 4 under final leak test   Completed (but NCs)  Completed but NCs  On-going, 9/14 vac subsectors validated  >100 Ics reclosed, 5/14 sub-sector under final leak test   Completed but NCs, 63 ICs insulated (yesterday)  1/3 done; see later  On-going  Completed (≈ 28%)  Desoldering almost completed; resoldering is on-going  > ½ sector completed  > ¼ of S12 ElQC tested, compatible with 30% of splices to redo   ½ of M lines open, all diodes containers open  4 in S34 reconnected, 2 in S45 almost reconnected  On-going 

  4. SEQUENCE AND STATUS Install DN200 Completed 100 % Open M sleeves Open ICs OK to open > 5 sectors >7 sectors 8 sectors Undo / Redo splices ELQC(new splices) Cancelled ≈ 4 sectors Machine Cu ELQCafter Cu mach. ELQC(old splices) > 3.5 sectors > 4 sectors > 3.5 sectors Consolidate Q diodes Availability of components ≈ 2.5 sectors Weld M Leak test M Close IC Final LT Insulate splices ELQCafter shunt Install shunts ≈ 1/5 sector ≈ 3.5 sectors ≈ 2.3 sectors ≈ 3.5 sectors ≈ 1 sector ≈ 2 sectors > 1.5 sector

  5. SMACC Progress report by activity • Opened interconnections in 8 sectors, > 7 sectors-eq are opened

  6. SMACC Progress report by activity • M line cutting : ≈ 5.5 sectorsequivalent • Replacing team trainedat the surface, will go in the tunnel nextweek • Takes in charge the insulationremovalactivities

  7. SMACC Progress report by activity • Desoldering : Completed in S56 & 67 & 78 and @ 65 % in S81 • Resolderingcompleted in S56 & 67 & 78 and @ 50% in S81 80 From last LSC (27.09.2013) 100 From last LSC (27.09.2013)  Rates are compatible with the 30 % of splices to redo and the baseline rate Courtesy H Prin

  8. SMACC Progress report by activity • Shunts are installedin ≈ 3.5 sectors-eq (1/2) Shunt weekly installation rate (4 weeks sliding average) • Rate in 81 is sticking to the baseline • «Last 10% effect» in 3 sectors • Delay reduced: < 1/2 week (nominal rate)

  9. SMACC Progress report by activity • Shunts are installedin ≈ 3.5 sectors-eq (2/2)

  10. SMACC Progress report by activity • Installation of insulation box: 56 & 67 are completed and 1/3 in 78, • 63 Ics are completed in 78 • Rate is still too low but improving (41 is the maximum achieved so far, average of the last 4 weeks: 33) • Progress curves will be integrated with the new baseline Courtesy H Prin / M Duret

  11. SMACC Progress report by activity • Quadrupole diodes • > 6 sectors are opened / ≈ 2.5 sectors are consolidated • Components to cover 78 and 1/3 of 81 (3.3 sectors) •  Not on the immediate critical path • Second order launched for critical components (expensive) •  Delivery expected in a month time • A third solution (reasonable price) is under investigation as a fall back solution • Visit of the 1st company today (Delay issues and also NC components) Courtesy L Grand-Clement / F Savary

  12. SMACC Progress report by activity • M Welding : 410 ICswelded, ≈ 2 sec-eq: • No welding this week to build a buffer of ICs ready to be welded (Announced @ last LSC) • Holes in 56 and 67 will be done next week • Work at a rate of 35-40 IC/week to start next week in 78 (About 70 ICs will be available on Monday), to sustain up to end 2013 • Will be integrated in the overall rebaselining

  13. SMACC Progress report by activity • M sleevesleaktesting : (320 ICs)are leaktested (≈ 1.5 sec-eq) • All possible subsectors of S56 (11/14) are leak tested • 9/14 subsectors are leak tested in 67 • Present situation will be included in the general rebaselining Courtesy P Cruikshank / L Mourier

  14. SMACC Progress report by activity • Reclosure of interconnections : On-going in 67 (priority) and 56 (> 1 sec eq), • 120 ICs are reclosed in 56 and 100 in 67 • Priority is on S67 • Global rate to increase and reachbaseline value with the reinforcement of part of the DN200 team

  15. SMACC Progress report by activity • Final leak test: Starting • 3 subsectors validated • 9 more under test (4 in 56 and 5 in 67) • Almost 1 sec eq • Results in 2 weeks time

  16. SMACC Progress report by sector QBQI.18R8 QQBI.27R8 • Main activities are on non-conformities • Overheated cable resoldered, now to be shunted and reinsulated • Uninstall shunts to remove the DFBAK shuffling module • Similarrepair (Sandwich) to beapplied in otherICs Courtesy M Duret, N Dalexandro, P Voisin, R Principe

  17. SMACC Progress report by sector • All non-problematic ICs are shunted, insulated and rewelded • Main activities are the leak test of M lines, the reclosure and the final leak tests • This sector should be the first to be ready for pressure test • Planned to be completely reclosed for end of November

  18. SMACC Progress report by sector • All non-problematic ICs are shunted • Main activities are the installation of the electrical insulation and the rewelding of M lines (to start next week)

  19. SMACC Dashboards • Openingisahead of schedule • Shuntingisalmost back on schedule • Criticalactivityis the insulation(Progress curvesoon to beincluded) • Welding and M leak test are limitedby release rate, confident that nominal rate canbeachieved, margin has been eaten up • Reclosure: Not yet nominal rate, to beincreased • Final leak test on-going for almost 1 sec eq

  20. SMACC Progress report by sector

  21. SMACC Dashboards

  22. SMACC Dashboards

  23. SMACC Progress report SIT • SIT • All cryomagnets are reconnected, except the 2 dipoles in S45 and the Q5L8 (SAM) • Standard reconnection will be done by the train when it will arrive • Just started: Interventions on SAM He level gauges: Accessible for MME intervention (Not critical) • On hold: Intervention on the triplets braid •  Disconnection of the DFBAK SHM that will start next Monday (See TE-CRG presentation) Courtesy N Bourcey, S Le Naour

  24. SMACC Progress report DFBA • DFBA: See TE-CRG presentation • Impact of interventions to fix the M bellows is under integration in the new baseline • DFBAK shuffling module to be disconnected • DFBAO on-hold ? Courtesy TE-CRG, TE-MSC and EN-MME

  25. SMACC Progress report DN200 • DN200 : Workcompleted • DN200 to install on removed cryomagnets and for the installation of the cryogenics BLM • Part of the team is staying and is trained to assist the opening/closure of interconnections and also the upgrade of the IC thermal shields Courtesy Jose Manu Gomes de Faria, A Musso and collaboration with DUBNA

  26. SMACC Dashboards Baseline: 38.1 % (30.9 %) Completed: 33.7 % (27.0 %) Delay 12 (11) days Baseline: 54.6 % (49.6 %) Completed: 45.8 % (38.7 %) Delay 30 (28) days  Delay stable  Delay stable Baseline: 56.6 % (47.4 %) Completed: 37.4 % (32.0 %) Delay 39 (38) days Baseline: 100 % (100 %) Completed: 100 % (88.2 %) Completed Not representative To be rebaselined

  27. SMACC Dashboards Progress: Baseline: 42.8% (36.3 %) Completed: 36.8% (30.1 %) Delay18 (18) days Stable ; Δbaseline ≈ Δcompleted

  28. SMACC Summary on progress Main 13 kA Splices:  Delay stabilised to 2 weeks Special Interventions:  Delay stable, new activities (DFBAK SHM) DFBA: To be rebaselined DN200: Completed SMACC:  About 3 weeks (stable) Delays are stable Nominal rate achieved these last 5 weeks !

  29. SMACC Main activities for the next 2 weeks • Sector 56 : • Work on non-conformities including installation of all shunts, completion of M welding • Disconnection of DFBAK SHM • Reclosure (not in priority) and final leak test • Sector 67 (Priority sector) • Leak test of M lines • Reclosure of interconnections and final leak tests • Sector 78 • Installation of electricalinsulation • M linesrewelding (35-40 ICs /wk) • Quadrupole diodes consolidation • DFBAs consolidation • Reconnection of Q5L8 • Sector 81 • Desoldering/ Resoldering of splices • Installation of shunts • Other sectors: • S12: ElQC of existingsplices • S23: Open busbarlines • S34: Opening of interconnections • S45: Reconnection of replacingmagnets and opening of diodes containers • Inspection of connection cryostats

  30. Conclusions • DN 200 installation is completed • Repair the overheated cable in 56 completed as planned • Delays are stabilised • Margin has been eaten up for someactivities (M welding, M leak test) • Solution isunderimplementation for the components of the quadrupole diodes • Issues: • Consolidate the splices production rates and increase the rate of installation of the insulationsystemskeepingquality • Impact of repair of DFBA bellows (SIT & Vacsubsectors) So far, not so bad …