Status of LS1 collimator maintenance. O . Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro. Main activities during the LS1. Collimator exchange (TCTP vs TCT, IR 1, 2, 5 and 8) Collimator installation (TCLP, TCL6 in IR1 and 5) New TCAPD (IR 3)
E N D
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro
Main activitiesduringthe LS1 • Collimator exchange (TCTP vs TCT, IR 1, 2, 5 and 8) • Collimator installation (TCLP, TCL6 in IR1 and 5) • New TCAPD (IR 3) • New installation commissioning • Collimator standard maintenance • Special maintenance • TIM / Robot intervention/observations • Alignment • Outlook O. Aberle – CWC
Collimatorexchange • New production of 16 + 4 TCTP • New production of 2 + 1 TCSP • New production of 2 + 1 TCAPD • Preparation of 2 spare TCLP • Preparation of 1 spare TCP • Layout modification in Pt. 8, removal of 2 TCTVB, shifting TCLIA • Pt. 1: Replacement of 4 TCT + by 4TCTP + installation of 2 TCLP and 2 TCT • Pt. 2: Replacement of 2 TCT + 2 TCLP by 4 TCTP • Pt. 3: Installation of 2 new TCAPD • Pt. 5: Replacement of 4 TCT + by 4TCTP + installation of 2 TCLP and 2 TCT • Pt. 6: Replacement of 2 TCS by 2 TCSP • Pt. 7: Remove first TCP on the right side and the three TCP on the left side during ventilation door installation (to prevent damage) and exchange the skewed TCP of IR7L (water cooling) • Pt. 8: Replacement of 2 TCT + 2 TCTVB by 4 TCTP O. Aberle – CWC
New installation commissioning • Check each collimator mechanics and electronics. • Full check of controll system • Slot and infrastructure (support, cabling, cooling water) • Installation and alignment • Vacuum connection and bake-out • Collimator standard maintenance O. Aberle – CWC
Collimatorstandardmaintenance • Check each collimator mechanics and electronics. • Cycle from out to in, to anti-collision and back to out. • Check 5th axis for clearance • Check water cooling flow • Check temperature sensors • Check switches, LVDT’s, resolvers, motors and drivers • Map sound profile for each collimator • Check rails • Check roller screws O. Aberle – CWC
Collimatorrollerscrewreplacement (2011-12) Dustanddebris in the end capandthehousing Some dry screwsregreased Uptodate 3 rollersscrewshavebeenexchanged. -No linear bearing -2 LVDT‘s -1 motor -2 switches O. Aberle – CWC
TIM andRobot intervention • Sound inspection of the collimators done with the TIM in S34 (23/24 April 2012). • Visual and acoustic inspections with camera can be useful in the future (TIM automatically, Telemax robot more flexible). • Vacuum disconnection testing with the Telemax robot on-going. • Use of robot for visual inspections/leak tests (He spray). • Profit from the long shutdown to verify the integration and do some hardware tests to confirm the procedures. O. Aberle – CWC
Alignment • Survey is working in the whole machine. • During smoothing, magnets will be aligned and collimators checked (and adjusted if needed). • IR 3 and IR 7 are equipped with additional targets for remote verification with the stretched wire. • New collimators (TCTP, TCSP, TCLP, TCT (TCL6) and TCAPD) will be aligned. • The TCP’s removed during the installation of the ventilation doors + the skewed TCP in IR7L to be checked (high radiation levels, how much deviation can be tolerated?). O. Aberle – CWC
Schedule – linked to LS1 LHC planning • Frame given by LHC planning, Julie is coordinating with Vacuum, transport, powering etc… • Cabling and control system availability • Installation readiness of new collimators O. Aberle – CWC
Schedule – details by Jerome O. Aberle – CWC
Schedule – linked to LS1 LHC planning • Work has just started • First ring collimators put back into operational statusTCLA.7L3.B2, TCP.6L3.B1, TCSG.5L3.B1 • A lot of work in parallel with surface preparation and installation activities. • J. Finelle from the vacuum team will take pictures when ever a collimator will be disconnected from the vacuum system. • All collimators will be checked for alignment errors, re-alignement has already started in several points. O. Aberle – CWC
Outlook • Improve the sound and image quality for the TIM, very powerful tool for the future. • Investigate on the capabilities of the Telemax or similarrobots for inspections and interventions. • Reference sound recording of all collimators? • Improve the accessibility to the screw (cap) (Phase 2!) • A regular check during long breaks and shut-downs with re-lubrication of the screw. • Check every slot for 5th axis motion limitations. • Sven De Man is the new reference person for the LHC tunnel situation concerning collimators O. Aberle – CWC