1 / 11

TRT HV System status and plans for LS1

TRT HV System status and plans for LS1. LPI Moscow, K. Zhukov. outline. HV problems in 2012. February 2012 problems.

debralynch
Download Presentation

TRT HV System status and plans for LS1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRT HV System status and plans for LS1 LPI Moscow, K. Zhukov

  2. outline

  3. HV problems in 2012

  4. February 2012 problems It’s seems there was shortage 450 V pin to the ground. It lead to some destruction of the board surface. Valera A. found some remains of electrolyte which caused the shortage. It was some defect in capacitor. The both crates 003 and 004 were recovered successfully. The opened part of the HV pins was covered with lacquer for protection. The PFCs were repaired in Dubna and set back in the PS3500s. To be check: both crates were in the same rack -> External factor?

  5. December 2012 problems In December we had problems with bottom crate 010 in Barrel. It happened twice during 10 days. In both cases damages were caused by some external debris or dust. It caused shortcut in the HV diodes -> diodes overheating -> breaks On the surface of the PS3500 board small debris of Al and dust were found. It points that we should think about HV rack cleanliness (see 2013 plans). The crate was recovered successfully. The surface of the board was covered with protection lacquer.

  6. HV crates status

  7. Over/undershoot events (Jolanta)

  8. HV system 2012 Spare HVM modules were received and calibrated. Ready to use. Spares pool is full. Enough components and spares. UPS line in USA15: There was problem that we had 10A protective element on UPS line and crate have 16 A fuse on input. If there’s trip of crate UPS line would trip. Now it’s OK. For two crates this protective element has 32 A limit. Vitaly Shutov started preparing HV firmware upgrade of SC508 to work with higher baud rate. All crate’s breaks were repaired successfully. November experience said when there’s HV crate trip it’s needed 40-60 mins (thanks to Andrei) to change it for spare one and switch them back to work with TRT.

  9. Timetable for LS1

  10. Timetable for LS1 Revise of all HV crate PS3500. Inviting Valera A. for a week to check PS3500 boards for any misbehaves. + over/undershot events explanation. Covering power supply boards with HV lacquer to prevent debris or dust shortcuts. Other maintenance. Cleaning HV racks from dust and debris. Thinking about new ventilation panels in HV racks. Maybe installing some filters. Calibrations of HV cells. Other measurements (stability, checking HV cables etc.) Firmware upgrade for higher baud rate. Devices for fuse burning. Possibility to use them in TRT (V. Kantserov)

  11. Thank you very much!

More Related