90 likes | 223 Views
Environmental, Safety, and Permitting. ESP Members: Emily Eidam Kurt Meehleis Wendy Parker Katie Russell- Lead. Permitting. Visit with Melissa Mormillo of Dowl Engineers Began list of permits Department of Natural Resources Municipality of Anchorage. Safety, Initial Concerns.
E N D
Environmental, Safety, and Permitting ESP Members: Emily Eidam Kurt Meehleis Wendy Parker Katie Russell- Lead
Permitting • Visit with Melissa Mormillo of Dowl Engineers • Began list of permits • Department of Natural Resources • Municipality of Anchorage
Safety,Initial Concerns • ADA paths • Transition • Pathways and Handrails • 30” vertical drop warrants a platform if steeper that 1:20 slope • Width of insulation for heated paths • Need about 5 feet on either side to prevent ice damming
Environmental • Seismic Hazard: High • Coastal Zone: Yes • Flood Hazard: Mostly No • Subdivision: Downtown Anchorage Urban Renewal • Wetlands: No • Propylene Glycol • Found product information
Permits • NPDES Construction General Permit • SWPPP • Right-of-Way Permit (MOA) • Alaska Coastal Management Program Consistency Determination • Water and Sewer Service • Storm Water Approval • Traffic Impact Analysis (Maybe) • Building Permit • Grading Permit • Access and Parking Agreements, or possibly a replat • Flood Hazard permit (Probably not) • Variance, depending on design • Parking Reduction (Maybe) • AWWU Private System Permit • Letters of Non-Objection
Working on…. • Environmental concerns • Permits • Cost • Filling out forms • Compilation • Checking paths for ADA compliance • Clear Zone Line • Based on ADT and Design Speed • Guardrail consideration
Helpful Resources • Y:\CE438_2008\Phase 2\ESP • Highway Specifications • Highway preconstruction manual • Municipality Maps • Links to PM&E, Municipality of Anchorage Standards and Specifications, and Design Criteria Manual
Group Requests • Cut and Fill volumes from each group for cost of permit • Once pods are placed, ADA slope compliance can be checked • More to come