An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Management Readiness Stephen Sawch, Assistant Director for Construction Management Conventional Facilities Advisory Committee Review March 10 –11, 2009

  2. Construction Preparations Outline • Safety – Critical Requirement • Construction Management Plan • Policies and Procedures • Construction Management Team • CF Field Office • External CM Oversight • Construction Readiness • CFAC Topics for Discussion • Path Forward

  3. Construction Safety • Objective – “Best in Class” Safety Program • Torcon - Proven Safety Record • Safety performance highest weighted selection criteria • OSHA Voluntary Protection Program (VPP Contractor) • Goal of DOE VPP & Star Worksite for LT • CF ESH Plan in Place • Regular meetings to continue improvements • Applied Lessons Learned in ESH Plan Development • CF Staff Taken OSHA 10 Hour Course • Our success measured by our Safety Performance

  4. Construction Management Plan • Construction Management Scope • Methods & Procedures to Meet Project Objectives • Quality Assurance Plan and CM Plan Work in Concert • CM Organization • Defines Responsibilities • ESH for Conventional Facilities • ESH Plan and CM Plan Work in Concert • Communication and Document Management • Define and Standardize Communication

  5. Construction Management Plan • Communication and Document Management cont’d • Establish Meeting & Reporting Requirements • Shop Drawing and RFI Routing • Project Control Software • Purchased Primavera Contract Mgr. (formerly Expedition) • CF Team trained on Contract Manager • Create, Share and Access Project Documents • Transmittals – Submittals – Correspondence • Web Based and is Used by Most Contractors • Manage Submittals • Submittals Logs & Dunning Letters

  6. Construction Management Plan • Project Control Software • Issue and Track Noncompliance • Build and Link Issue Files with Documents • Field Inspection & Oversight • Develop Project Checklist • Oversee Day to Day Activity • Document Nonconformance • Testing & Commissioning • Test Record Index • Commissioning Contractor

  7. Construction Management Plan • Acceptance and Transition to Operations • Testing & Training Complete • O&M Documents Available • Punch List Preparation • BORE – Beneficial Occupancy Readiness Evaluation • Change Control & Configuration Management • Technical Changes • Reviewed & Approved • Documented (ECN –Engineering Change Notice) • Maintain As-Built Drawings – Monthly Updates Part of Pay Req.

  8. CF Procedures Manual • Used BNL’s Plant Engineering Policies & Procedures as basis for CF Procedures Manual • Worked with Quality Assurance identified applicable Policies • Successfully used for CFN • Transmittals, submittals, RFIs, reports, inspections and closeout • Integrated Contract Manager Software into CF Procedures Manual (Primavera)

  9. CF Procedures Manual

  10. CF Procedures Manual

  11. Procedures – Inspection Forms

  12. LT- CF Construction Team • Staffing Requirements Determined • Roles and Responsibilities Identified • Project Team Established • 3 Lead Engineers Hired • Administrative Assistant Hired • Construction Engineer/Civil & Electrical Inspectors Hired • Last Hire - Mechanical Inspector – Currently Interviewing • Anticipate Staff Augmentation Requirements • Augment with CM Firm (Liro/Gilbane) Staffing • Inspectors/Clerk of Works/Administrative Assistant/Others

  13. Construction Staffing Requirements

  14. Construction Management Organization

  15. Establish LT Field Office • Field Staff of Approximately 10 • Trailer Purchased – Delivery March 23 • FFE Ordered • Utilities – Power and Communications Available • Services Required – Sanitary, Cleaning, Trash • Signage Plan Complete – Ordered Shortly • Occupy April 6

  16. LT Field Office Site Plan

  17. LT Field Office Layout

  18. LT Field Office Furniture

  19. External CM Construction Services • Liro/Gilbane Provided Design Phase CM Services • Estimating • Value Engineering • Scheduling • Market Analysis • Liro/Gilbane Hired for Construction Phase Services • Construction Delivery Changed – CM Limited Role • Monthly Construction Management Assessment • Staff Augmentation (As Required)

  20. External CM Construction Services Part A: Project Management Review • CM Assessment Scope • Kick-off Meeting To Initiate Development of Construction Management Procedural Review (CMPR) • Evaluation of CF Procedures • Evaluation of GC Schedule of Values • Assist In Development of Deliverables List • Monthly Site Visits With Conventional Facilities Management Team (CFMT) • Attend Progress Meetings

  21. External CM Construction Services Part A: Project Management Review - Continued • Produce Construction Management Procedural Review (CMPR) - A Monthly Report Outlining: • Administration (Staffing, Document Control, etc.) • Engineering (Submittals, RFIs) • Quality (Testing and Inspection) • Change Management Process (Review, Approve & Document) • Closeout (Warranties, As Built drawings, O&M Manuals, etc.) • Evaluate and Provide Recommendations Regarding Management of Construction

  22. External CM Construction Services Part B: Staff Augmentation • Anticipated Staff Augmentation Positions • Clerk of the Works (Office Engineer from CM) • Civil/Arch/Mech/Elect Inspectors (from CM) • Structural Engineer (from CM) • Administrative Assistant (from BNL)

  23. Construction Readiness • BNL Warehouse Relocation- Complete • Site Prep - Civil - Complete • Site Prep - Electrical - Complete • Site Logistics - Complete • Site Access Planning - Complete • Visitor Badging/Training Facility Upgrade – Summer 09

  24. Torcon Site Logistics Plan

  25. CFAC Topics for Discussion • Successful Ring Building Construction Start • How can we ensure a safe and smooth start for Torcon • Establish Communication Channels • Collaborative Approach to Site Logistics Planning • Timely Response to RFIs & Submittals • Streamline Site Access for Contractors/Vendors • Streamline Equipment Inspection Process

  26. CFAC Topics for Discussion • Potential Acceleration of Ring Building Schedule • Confirm Feasibility by Torcon • Confirm Funding Availability • Benefit from Current Market Conditions

  27. CFAC Topics for Discussion • Coordination w/ the Accelerated LOB Schedule • Ensure LOB Design Meets Schedule • Prepare Revised Construction Program to Accommodate LOB Design • Consider Contracting Options to Minimize Impacts

  28. Path Forward • Hire Mechanical Inspector – Complete Training • Implement ‘Best in Class’ Project Safety Program • Work with Torcon to Facilitate Mobilization • Work with Torcon to Implement Project Procedures • Establish effective communication, planning and execution • Interface CM Software Programs • NSLS-II Contract Manager • Torcon Prolog • Continuous improvement of CF Procedures Manual