An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. U.S Army Corps of Engineers Savannah District OP-Navigation.ppt

  2. Civil Works & Navigation Boundaries SC Savannah R. ATLANTIC OCEAN GA Savannah Harbor AIWW Brunswick Harbor St. Mary’s R. OP-Navigation.ppt

  3. Navigation Projects • Sav’h Harbor32.5 Miles • AIWW161 Miles • Brunswick 24 Miles Total 217.5 Miles OP-Navigation.ppt

  4. ScheduledFY07 Dredging Work in Savannah District South Atlantic Division Hopper Dredge Maintenance Dredging OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP BO 9 BO 10/15 FY07 Savannah & Brunswick Entrance Chl Sea Turtles-screens & observers Est. 2,000K CY Hydraulic Pipeline Dredge Maintenance Dredging BO 15 Savannah & Brunswick Inner Harbor Striped bass spawning Est. 5,180K CY Hydraulic Pipeline Dredge New Work Dredging Brunswick Deepening Sta 20 to 46, E. River to 36 ft. Est. 5,063K CY OP-Navigation.ppt

  5. Savannah District FY 07 Hopper Dredge Program OP-Navigation.ppt

  6. ScheduledFY07 Dredging Work in Savannah District South Atlantic Division Hopper Dredge Maintenance Dredging OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP BO 9 BO 10/15 FY07 Savannah & Brunswick Entrance Chl Sea Turtles-screens & observers Est. 2,000K CY OP-Navigation.ppt

  7. Savannah District • Project: Savannah Entrance Channel • Type of work: Maintenance • Depth: 42/44 ft • Width: 600 ft • Length: 11.4 miles • Quantity: 1.0 MCY • Type of Material: sand/silt/clay • Placement Areas: EPA approved ocean site and near shore sites • Distance to Placement Area: up to 11.5 miles • Type of Equipment: Hopper • Small Business Set Aside: No • Last Dredged: FY06 • Environmental Window: Dec 15- March 31 • Reason for Window: Right Whales and Sea Turtles OP-Navigation.ppt

  8. Savannah District • Project: Brunswick Entrance Channel • Type Work: Maintenance • Depth: 32/36/38 feet • Width: 500 feet • Length: 16.8 miles • Quantity: 1.0 MCY • Type of Material: Sand/silt/clay • Placement Areas: EPA approved ocean site and near shore sites • Distance to Placement Area: up to 19 miles • Type of Equipment: Hopper • Small Business Set Aside: No • Last Dredged: FY06 • Environmental Window: 15 Dec-13 March • Reason for Window: Right Whales and Sea Turtles OP-Navigation.ppt

  9. Savannah District FY07 Hydraulic Cutter Head Dredge Program OP-Navigation.ppt

  10. ScheduledFY07 Dredging Work in Savannah District South Atlantic Division OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP Hydraulic Pipeline Dredge Maintenance Dredging BO 15 Savannah & Brunswick Inner Harbor Striped bass spawning Est. 5,180K CY Hydraulic Pipeline Dredge New Work Dredging Brunswick Deepening Sta 20 to 46, E. River to 36 ft. Est. 5,063K CY OP-Navigation.ppt

  11. Savannah District • Project: Savannah & Brunswick Inner Harbors • Type of work: Maintenance • Depth: (SH)40/46 ft, (BH)30/36 ft • Width: (SH)500 ft, (BH)350/400 ft • Length: (SH)21.3 miles, (BH)3 miles • Quantity: 5.2 mcy • Type of Material: sand/silt/mud • Placement Area: Upland placement sites • Distance to Placement Area: up to 2 miles • Type of Equipment: Hydraulic cutterhead pipeline • Small Business Set Aside: Yes • Last Dredged: FY06 • Environmental Window: (SH) March 15-May 30 (above Station 63+000) (BH)April 1-August 1 • Reason for Window: (SH)Striped Bass Spawning (BH) Least tern nesting OP-Navigation.ppt

  12. Savannah District • Project: Brunswick Deepening Inner Harbor • Type Work: Unclassified • Depth: 36 feet • Width: 400 feet • Length: 12.3 miles • Quantity: 8.0 MCY • Type of Material: Sand/silt/clay • Placement Areas: New Bird Island & Andrews Island • Distance to Placement Area: up to 5 miles • Type of Equipment: Hydraulic cutterhead pipeline • Small Business Set Aside: No • Last Dredged: N/A • Environmental Window: None • Reason for Window: N/A OP-Navigation.ppt