An Overview of ITS in PA. Matthew Kozsuch, P.E. President, ITSPA. ITS Tri-Chapter Meeting Herndon, VA July 9, 2008. PennDOT TSOP (2005). TSOP-01: Inter-Agency Incident Reporting Sys TSOP-02: Road Condition Reporting System TSOP-04: Incident Mgmt Traveler Info TSOP-06: Roadway Weather Mgmt
E N D
An Overview of ITS in PA Matthew Kozsuch, P.E. President, ITSPA ITS Tri-Chapter Meeting Herndon, VA July 9, 2008
PennDOT TSOP (2005) • TSOP-01: Inter-Agency Incident Reporting Sys • TSOP-02: Road Condition Reporting System • TSOP-04: Incident Mgmt Traveler Info • TSOP-06: Roadway Weather Mgmt • TSOP-09: STMC and TMCs • TSOP-10: ITS Equipment Maintenance • TSOP-13: ITS and IT ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
Statewide ITS Strategic Plan • Fresh Look at ITS in PA • Update to be Complete Summer 2008 • ID Action Items ITS Standards New ITS Design Standards Recently Completed (PennDOT and Turnpike) ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
511 • Bidding Closed as of July 3, 2008 • Reviewing proposals now • Anticipated NTP October 2008 • Initial System Operational June 2009 Statewide ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
PennDOT District 6 Philadelphia Area • 24 x 7 TMC • 190 CCTV Cameras – 62 add’l programmed • 72 DMS – 12 add’l programmed • Incident Detection • EZ Pass Tag Readers for Travel Time Info. • Integrated Corridor Projects ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
PennDOT District 11 Pittsburgh Area • 24 x 7 TMC • 95 CCTV Cameras – 65 add’l programmed • 16 DMS – 12 add’l programmed • 8 HARs • Truck Height Warning Systems for Tunnels • Anti-Icing System ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
PennDOT District 8 Harrisburg Area • 24 x 7 TMC • 31 Permanent DMS – 30 add’l planned • 15 Portable VMS • 41 CCTV Cameras – 110 add’l planned • 14 HARs ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
PA Turnpike Commission System-Wide • 24 x 7 Ops Center • 20 CCTV Cameras – 21 add’l programmed • 21 DMS – 27 add’l programmed • 41 HARs – 2 add’l programmed • Truck Rollover Warning System • 4 RWIS – 8 add’l programmed • New 12,000 s.f. Ops Center Under Design ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
PA Turnpike Commission Fog Detection and Warning System • 10 Mile Section • 26 Variable Speed Limit Signs • 9 RWIS • 9 Traffic Flow Detectors • 9 CCTV Cameras • 11 DMS ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
MPOs • Delaware Valley Regional Planning Commission • RIMIS (Regional Integrated Multi-modal Information Sharing) • Traffic Signal Initiative ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
DVRPC Regional Architecture, 2001 ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008
ITSPA Chapter • Annual Meeting Sept 11th and 12th in King of Prussia, PA • Western, Central, Eastern Area Meetings • Golf Outing in August with MASITE • First ITSPA Scholarship Awarded Recently ITS Tri-Chapter Meeting - Herndon, VA - July 9, 2008