An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PHOENICS User Conference 2004 “Using CFD for Sports Arena and Stadia Design” Eric Jal Connell Wagner, Melbourne, Australia 3-5 May 2004 - Melbourne, Australia

  2. Introduction • Occupancy issues in sports stadia and leisure complexes becoming paramount • Increasingly common to use CFD in the design process to assess:- • natural ventilation (comfort) • mechanical ventilation • pitch ventilation • exhaust discharge • fire safety

  3. Project Case Studies • PHOENICS CFD code has been used • TECPLOT used for results visualisation • Several case studies will be presented:- • Telstra Dome - Melbourne, Australia • Lang Park - Brisbane, Australia • MCG - Melbourne, Australia • Wembley Stadium - London, UK • MSAC Extension - Melbourne, Australia • Oasis Arena - Sydney, Australia • Casey Aquatic Centre - Melbourne, Australia

  4. Case Study - Telstra Dome Telstra Dome - Melbourne, Australia

  5. Telstra Dome - Background • Located within the Melbourne Docklands urban re-development precinct • Designed and built within 2½ years • Used for AFL/soccer/rugby cricket and concert events • Seating capacity of 52,000 including a movable lower stand tier of 12,500 seats • A 167m by 132m retractable pitch roof (can open & close in under 10 minutes)

  6. Telstra Dome - Design Scope • When roof is closed it becomes a fully enclosed all weather “indoor” facility • Occupancy comfort and life safety needs consideration • Other similar stadia normally include mechanical ventilation • Concerns about large capital costs and ongoing energy consumption led to a design study for justifying an effective passive (natural) ventilation solution

  7. Telstra Dome - Design Analysis Natural Ventilation : Full Stadium - No Wind (35oC Day) - Roof Closed

  8. Telstra Dome - Design Analysis Fire Safety : 15MW Pitch Fire - Roof Closed

  9. Telstra Dome - Analysis Summary • Location & spacing of roof vents optimised • Architectural design of roof vents and facade openings promote air movement which enhances occupant comfort for a wide range of environmental conditions • Temperature rises around bowl arena not deemed excessive (within 5oC) assuming the patrons are suitably attired consistent for a naturally ventilated facility • Life safety tenability criterion also satisfied

  10. Case Study - Lang Park Lang Park Stadium - Brisbane, Australia

  11. Lang Park - Design Scope • Recently redeveloped for increased seating capacity • Designed to be capable in the future of incorporating a retractable pitch roof • CFD modelling was conducted to determine natural ventilation openings necessary to provide spectator comfort • Scenarios simulated for different environmental conditions for both an open stadium and with a pitch roof

  12. Lang Park - Design Analysis Natural Ventilation : Full Stadium - No Wind (32oC Day) - No Roof

  13. Case Study - Wembley Stadium Wembley Stadium - London, UK

  14. Wembley Stadium - Design Scope • Currently in the process of being upgraded and redeveloped • Engaged in fire engineering design review to address issues associated with the Building Regulation compliance • CFD modelling was conducted for fire scenarios within the concourse atrium • Scenarios also performed for assessing mechanical smoke extraction system requirements within service “ring road”

  15. Wembley Stadium - Design Analysis Fire Safety : 3MW Concourse Atrium Fire

  16. Wembley Stadium - Design Analysis Fire Safety : 20MW Underground Service “Ring Road” Fire

  17. Case Study - MSAC Extension MSAC Extension - Melbourne, Australia

  18. MSAC Extension - Design Scope • Venue is to be upgraded in readiness for 2006 Commonwealth Games • Outdoor pool arena is being proposed with lightweight roof and open sides • For energy impost and sustainable development considerations natural ventilation is postulated • CFD modelling undertaken in order to demonstrate the viability of design

  19. MSAC Extension - Design Analysis Natural Ventilation : No Wind (15oC Day)

  20. Case Study - Casey Aquatic Centre Casey Aquatic Centre - Melbourne, Australia

  21. Casey Aquatic Centre - Design Scope • Ventilation within an indoor pool needs to ensure sufficient “fresh” air requirements • Necessary for removal of water vapour (RH control) and chemical vapours • Different mechanical ventilation systems configurations were analysed with CFD • Establish air movement distribution and show undesirable stagnant flow regions

  22. Casey Aquatic - Design Analysis Mechanical Ventilation : “Push-Pull” System

  23. Case Study - Oasis Arena Oasis Arena - Sydney, Australia

  24. Oasis Arena - Design Scope • Performance based approach used to satisfy BCA fire design requirements • CFD modelling was conducted to ensure indefinite tenability conditions are maintained within concourse/vomitories • Provide assistance in optimising the smoke extraction system in terms of size and capacity • Consequently gives indication of expected capital cost outlay of mechanical systems

  25. Oasis Arena - Design Analysis Fire Safety Analysis : 10MW Stage Fire

  26. Case Study - MCG Redevelopment MCG Redevelopment - Melbourne, Australia

  27. MCG Redevelopment - Design Scope • Northern side of stadium currently being redeveloped for utilisation at the 2006 Commonwealth Games • Several CFD modelling studies done for:- • Ventilation (thermal comfort) • Plant room exhaust dispersion • Pitch ventilation • Fire life safety • Onus of design process to maximise ESD initiatives and optimise resource efficiency

  28. MCG Redevelopment - Design Analysis Plant Room Exhaust : 4m/s Northerly Wind

  29. MCG Redevelopment - Design Analysis Pitch Ventilation : 4m/s Northerly Wind

  30. Conclusions • Project case studies have shown the use of CFD as an important part of the engineering design process of sports stadia/arenas • Issues relating to ventilation, occupancy comfort and life safety can be addressed • Facilitates ‘sustainable design technology’ solutions by avoiding/limiting mechanical ventilation energy usage as far as possible • Can be promoted as world’s ‘best practice’ and used as a benchmark for stadia design