Staffing, FTEs, and other management measurables

Staffing, FTEs, and other management measurables. Importance of accurate staffing:. Direct effect on labor costs Indirect effects on employee satisfaction, absenteeism, overtime (not to mention stress!! ). Here’s a question for you:.

garry
Download Presentation

Staffing, FTEs, and other management measurables

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Staffing, FTEs, and other management measurables

  2. Importance of accurate staffing: • Direct effect on labor costs • Indirect effects on employee satisfaction, absenteeism, overtime (not to mention stress!!)

  3. Here’s a question for you: • Staff of a tray-assembly line produce four trays per minute and 180 trays each meal. Three meals are served each day. The line has six employees. How many labor hours are needed to staff the trayline? • A. 2.25 • B. 4.50 • C. 6.00 • D. 13.50

  4. Another one: Calculate the minutes of labor needed per meal for a facility with the following data: Position • Cook I • Cook II • Relief cook • Aide I • Aide II • Relief aide • Supervisor Hrs worked • 80 • 80 • 64 • 80 • 80 • 64 • 80 Number of meals served Jan 1 to Jan 14 = 2,505 meals

  5. These are often quoted benchmarks: • Meal equivalents/Labor hours • Minutes labor/total meals • Total meals served/day divided by labor hours/day • Trays/minute • Payroll cost/meals served • Sales/square foot • FTEs/day or FTEs/week • Food cost % • Labor cost % • Clinical consults/patient day

  6. Productivity indicators you want to remember for RD exam. FTEs, one FTE = 8 hours a day, 40 hours a week, 2080 hours a year. Some foodservice indicators: • Labor hours per meal = Number of labor hours/number of meals • Labor minutes per meal = Labor hours per meal X 60 minutes per hour • Meals per labor hour = Number of meals served/Labor hours for same time period. • Food cost %; Labor cost % • Cost per serving Clinical productivity indicator: Patient contacts per hour worked = No. of patient/resident contacts per clinical labor hours worked.

  7. Calculating FTEs • How many people do you need to feed 100 people, 3 meals/day? • (Industry suggests you should be able to produce 3.5 meals per hour) • 3.5 meals per hour = 17 labor minutes/meal (60 divided by 3.5 = 17) • 300 meals/day X 17 minutes/meal = 5,100 minutes/day. • 5,100 minutes/day divided 60 minutes/hour = 85 hours/day needed to produce 300 meals.

  8. Then… • 85 hours per day divided by 8 hours/day = 10.6 positions needed or 11 FTEs. • Workers are only supposed to work 8 hours a day or get paid overtime. One FTE = 8 hours a day, 40 hours a week, 2,080 hours a year. So 11 FTEs… • Is this really enough? • Maybe not. If you want to make sure there are benefits for all, it is not. • Then you might multiply 11 x 1.55 = 17 positions.

  9. Classification of labor hours • Productive hours: • Worked hours • Overtime • On-call hours worked • Continuing ed • Orientation/training • Non-productive: • Vacation • Holiday • Sick time • Jury duty • Work injury • Paid leave Paid hours include both productive and non-productive hours

  10. Meals per productive hour • A. subtract the non-productive hours and calculate as usual • B. typical ratio might be that 10% of total hours are non-productive; subtract 10% of your FTE and calculate as usual

  11. Here’s another: • There are seven foodservice employees in the patient tray assembly unit at a hospital where the patient tray census is ~350. If 1.5 hours is allowed, a feasible productivity goal for the unit is to assemble how many trays per minute? • A. 2 • B. 3 • C. 4 • D. 5