1 / 24

Vacuum observations during the 7 5 and 50 ns bunch spacing operation (MD 17-20 Nov 2010)

Vacuum observations during the 7 5 and 50 ns bunch spacing operation (MD 17-20 Nov 2010). V. Baglin, G. Bregliozzi, P. Chiggiato, J-M. Jimenez, G. Lanza. CERN TE-VSC , Geneva. 1. 75 ns bunch spacing 2. 50 ns bunch spacing 3. Test r amp with 50ns_109b_12_90_12bpi10inj 2. Conclusion.

gavin
Download Presentation

Vacuum observations during the 7 5 and 50 ns bunch spacing operation (MD 17-20 Nov 2010)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vacuum observations during the 75 and 50 ns bunch spacing operation (MD 17-20 Nov 2010) V. Baglin, G. Bregliozzi, P. Chiggiato, J-M. Jimenez, G. Lanza CERN TE-VSC, Geneva 1. 75 ns bunchspacing 2. 50 ns bunchspacing 3. Test rampwith50ns_109b_12_90_12bpi10inj 2. Conclusion LHC Beam Commissioning WG- 23 Nov 2010

  2. 1. 75 ns bunch spacing LHC Beam Commissioning WG- 23 Nov 2010

  3. Stacking 48b to 680 with gaps of 1.85 microsec • Injection of 24+24 bunches separated by 75 ns and 225 ns between b24 and b25 • 1.85 µs between trains • Machine full with 2x680b after 14 injections LHC beam commissioning 19 nov 2010

  4. Stacking 48b to 680 with gaps of 1.85 microsec • Average bunch current 0.9 E11 p/bunch • Below interlock level (4e-7 mbar) when machine filled with 2 x 680 b • Mainly pressure increases at D1 and less in other areas • Stayed for ~ 2h before beam dumped LHC beam commissioning 19 nov 2010

  5. Conditionning at 680b1+680b2 • Reduction of ~ a factor 2 at D1 LSS2 and LSS8 LHC beam commissioning 19 nov 2010

  6. Pressure increase with machine full • Linear trend in pt1, 3 • Except for pt2, pt 8 where threshold at ~ 70 mA (248+248 b) • No pressure increase in pt5 & 7 LHC beam commissioning 19 nov 2010

  7. Pressure increase comparison • Threshold at 9-10 1010 p/b for 75 ns beams • Beam conditioning Losses ? LHC beam commissioning 19 nov 2010

  8. VGPB.2.5L3.B BPMWE Ellipse 52x30 mm LHC beam commissioning 19 nov 2010

  9. 2. 50 ns bunch spacing LHC Beam Commissioning WG- 23 Nov 2010

  10. Pressure increase comparison • Higher slope for 50 ns than 75 ns • A factor 2 between the slopes LHC beam commissioning 19 nov 2010

  11. 3. Test ramp with 50ns_109b_12_90_12bpi10inj LHC Beam Commissioning WG- 23 Nov 2010

  12. Fill 1500 – 19th November • Only SR desorption • in LSS2 • in LSS3&5 • In LSS6&7 LHC beam commissioning 20 nov 2010

  13. Fill 1500 – 19th November • Pressure increases at VGI in A4L1 • But remains lower than 7E-10 mbar SR at ~ 2 TeV Bunch length increases Bunch length decreases during ramp Up to 1 TeV LHC beam commissioning 20 nov 2010

  14. Fill 1500 – 19th November • During ramp, bunch length decrease at 19:36 and flattens at 19:40 LHC beam commissioning 20 nov 2010

  15. Fill 1500 – 19th November • Some activity in MKIR8 intermodule stimulated by ramp and SR • Start ramp, pressure increase starting from ~ 550 GeV (19:36) • But flattens at 800– 1000 GeV (19:40) SR at ~ 2 TeV Bunch length decreases during ramp Up to 1 TeV Bunch length increases LHC beam commissioning 20 nov 2010

  16. Same ramp the 31th October LHC Beam Commissioning WG- 23 Nov 2010

  17. Fill 1459 – 31th October • 50ns_109b_12_90_12bpi10inj - Trains well separated i.e. no discussion between trains • Pressure up to 2e-8 mbar LHC beam commissioning 20 nov 2010

  18. 4. Conclusions LHC Beam Commissioning WG- 23 Nov 2010

  19. Conclusions • 2x680 b were injected with 75 ns, pressure remained below interlock level • Beam conditioning was observed during ~ 2h storage time • At 75 ns, threshold around 9-10 1010 p/bunch • At 50 ns, the pressure rise per mA is ~ 2 x the 75 ns pressure rise per mA • The test ramp of 50 ns_109b_12_90_12bpi10inj exhibits no pressure rise larger than • 7 10-10 mbar • Beam conditioning is ongoing LHC beam commissioning 20 nov 2010

  20. Backup slides : Same ramp the 31th October LHC Beam Commissioning WG- 23 Nov 2010

  21. Fill 1459 – 31th October • 50ns_109b_12_90_12bpi10inj - Trains well separated i.e. no discussion between trains • Pressure up to 2e-8 mbar LHC beam commissioning 20 nov 2010

  22. Fill 1459 – 31th October • 50ns_109b_12_90_12bpi10inj - Trains well separated i.e. no discussion between trains • Pressure increases due to ecloud in the 1e-9 mbar region SR at ~ 2 TeV LHC beam commissioning 20 nov 2010

  23. Fill 1459 – 31th October • 50ns_109b_12_90_12bpi10inj - Trains well separated i.e. no discussion between trains • Pressure 4e-9 mbar SR at ~ 2 TeV LHC beam commissioning 20 nov 2010

  24. Fill 1459 – 31th October • 50ns_109b_12_90_12bpi10inj - Trains well separated i.e. no discussion between trains SR at ~ 2 TeV LHC beam commissioning 20 nov 2010

More Related