An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Contractor QC Wesley Glass Kentucky Transportation Cabinet 2007 KAHC/KYTC Meeting Bowling Green/Lexington, Kentucky

  2. Contractor QC What is Required? • 23 CFR 637

  3. Contractor QC • Frequency Guide Schedule • Identification of Location for Sampling and Testing • Specify attributes to be inspected

  4. Contractor QC Quality Control sampling & testing may be used as part of acceptance decision provided that:

  5. Contractor QC • Qualified labs & personnel • Validated by verification samples • Evaluated by an IA program • Establish a dispute resolution system

  6. Contractor QC Kentucky’s Use of Contractor’s Results for Acceptance • HMA • Soil Embankment and Subgrade • Concrete Pavement • Concrete – Structural/Non Structural • Aggregate • Striping • Bridge Coating

  7. Contractor QC • HMA – Well Established • Attributes – Volumetrics & Density • Sampling – Plant and Roadway • Lot – Four Contractor/One State • Quality Measure – Individual Value • Pay – Incentive/Disincentive

  8. Contractor QC • Soil Embankment and Subgrade– Special Note • Attributes – Density & Moisture • Sampling - Roadway • Lot – Four Contractor/One State • Quality Measure – Individual Value • Pay – Accept/Reject

  9. Contractor QC • Concrete Pavement – Special Note • Attributes – Air, Slump, Temp, & Compressive Strength • Sampling - Jobsite • Lot – Eight Contractor/One State • Quality Measure - PWL • Pay – Incentive/Disincentive

  10. Contractor QC • Concrete Structural/Non Structural – Special Note • Attributes – Air, Slump, Temp, & Compressive Strength • Sampling - Jobsite • Lot – Eight Contractor/One State • Quality Measure – Individual Value • Pay – Accept/Reject

  11. Contractor QC • Aggregate – Special Note • Attributes – Gradation, Minus 200 and Density • Sampling - Jobsite • Lot – Four Contractor/One State • Quality Measure – Individual Value • Pay – Accept/Reject

  12. Contractor QC • Striping – Special Notes • Attributes - Retroreflectivity • Sampling - Roadway • Lot – Segments (1/5 of days striping) • Quality Measure – 80% exceed required minimum • Pay - Disincentive

  13. Contractor QC • Bridge Coating – Special Note • Attributes – Profile, Test Patch, Dry Film Thickness, Visual • Sampling - Jobsite • Lot – Quality Control Points • Quality Measure - Inspection • Pay – Accept/Reject

  14. Contractor QC • On Down the Road! • Total Project QC • Special Note for Contractor Quality Assurance Program

  15. Contractor QC

  16. Contractor QC

  17. Contractor QC