1 / 37

Mount Vernon Yacht Club Long Range Projects

Mount Vernon Yacht Club Long Range Projects. Projects under consideration. Replace/repair bulkhead along parking lot Dredging Replace/Upgrade of C and D Docks Include upgrade of electric for E Dock Resurface parking lot, driveway. Bulkhead -- 450 Linear Feet.

gella
Download Presentation

Mount Vernon Yacht Club Long Range Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mount Vernon Yacht ClubLong Range Projects

  2. Projects under consideration • Replace/repair bulkhead along parking lot • Dredging • Replace/Upgrade of C and D Docks • Include upgrade of electric for E Dock • Resurface parking lot, driveway

  3. Bulkhead -- 450 Linear Feet

  4. Bulkhead – Possible Soil Loss

  5. Bulkhead – Possible Soil Loss

  6. Bulkhead – Possible Soil Loss

  7. Bulkhead – Sheeting • Old, deteriorating sheeting • 25+ years old • 2”x10” • Rotting?

  8. Bulkhead – Sheeting

  9. Bulkhead – Sheeting

  10. Bulkhead – Sheeting

  11. Bulkhead – Sheeting

  12. Bulkhead – Sheeting

  13. Bulkhead Replace or Repair • Two experts recommend replacing entire bulkhead • Cost estimates range from $400/ LF and up • There are 450 linear feet of bulkhead ($180k) • Permitting could get extensive and expensive • Three experts recommend replacing only the sheeting • Replace all sheeting with 3x10 boards ($90k) • Piles, whalers (Cross timbers) and tie rods are in good shape • Permitting should be simple – do job gradually as a repair • MVYC expert (Ricky) recommends replacing only the bad sheeting • Do it as normal maintenance – no permitting • In-house project, a few hundred dollars at a time • We will investigate these options over the summer

  14. Bulkhead Replace or Repair

  15. Dredging • Need to establish “maintenance” level for future dredging • Need to start permit process now • 6 months to 1 year to obtain permit • Permit process will be more difficult from 2013 on • Economical disposal of spoils until end of 2012 • Don’t think VMRC will exercise jurisdiction over man-made boat basin • Army Corps of Engineers approval may be uncomplicated • Fairfax County permit process is unknown • Team has been organized to apply for permit

  16. Dry Marina – January 2006

  17. Dry Marina – January 2006

  18. Dredging – Estimated Costs

  19. C & D Docks + Electrical for E Dock

  20. C Dock

  21. Finger Pier – C Dock

  22. C Dock Electrical Service

  23. D Dock

  24. E Dock

  25. New Pedestals for C, D and E DocksProvide electrical and water service

  26. C Dock Layout

  27. D Dock Layout

  28. C & D Docks + Electrical for E Dock Considerations: • Complete replacement of C&D a significant outlay ($186k) • Need longer fingers plus more piles to accommodate medium-sized boats on south side of C Dock • Main decking 6 years old • At a minimum finger piers need replacing on both docks • Need updated electrical and plumbing • Add pedestals for C Dock (8), D Dock (1), E Dock (4) • Install new Dominion Power 200 amp panel for C and D docks • Install electrical service from new panel to C and D Docks • Feed E Dock from house panel • Connect pedestals to electric and water sources • Could be a lengthy permit process

  29. C & D Docks plus E Dock Electrical

  30. Parking Lot/Driveway resurfacing • Should be done, but only after heavy equipment work is finished on site • Dredging • Bulkhead work • Material delivery for C & D

  31. Parking Lot/Driveway resurfacing

  32. Parking Lot/Driveway resurfacing

  33. Parking Lot/Driveway resurfacing

  34. Parking Lot/Driveway resurfacing

  35. Project Capital Cost Summary MinMax • Bulkhead • repair/replacement $ 0 - $ 90,000 $185,000 • Dredging 210,000 210,000 • C & D Dock repair/replace 71,000 186,000 • Parking lot resurfacing 75,000 75,000 • Totals $356,000 - $446,000 $656,000

  36. Recommended sequence Depends on approaches, but in general: • Beging Dredging effort • Apply for dredging permit now • Permit process will be more difficult from 2013 on • There is a time constraint on economics of spoils disposal (end of 2012 calendar year) • Bulkhead repair/replace – investigate extent of problem • C & D Dock repair/replace, + electrical service for E Dock • Set panel and run new electric service for C, D and E Docks (Could be done at any time) • Resurface parking lot after all heavy equipment work for dredging, bulkhead and dock work is finished

More Related