GLYNN COUNTY. Project Commencement Public Meeting East Beach Utilities Infrastructure Improvements December 5, 2007 7:00 p.m. CASINO Room 108. Glynn County Board of Commissioners. INTRODUCTION and OPENING REMARKS. Sanitary Sewer Replace sagging and reverse grade sewer lines
E N D
GLYNN COUNTY • Project Commencement • Public Meeting • East Beach Utilities Infrastructure Improvements • December 5, 2007 • 7:00 p.m. • CASINO Room 108
Glynn County Board of Commissioners INTRODUCTIONand OPENING REMARKS
Sanitary Sewer Replace sagging and reverse grade sewer lines Proactive approach to reduce inflow and infiltration (I&I) problems Primary source of I&I is main lines and service laterals EAST BEACH OBJECTIVES
EAST BEACH OBJECTIVES Sanitary Sewer • Reduce odor problems • Reduce maintenance service calls for East Beach area • Provide for better wastewater transmission via a pump station behind the Coast Guard station
EAST BEACHOBJECTIVES Water System • Improve pressure within the system and fire flow capabilities Storm Drainage System • Improve drainage to relieve localized flooding
Contractor is Douglas Electric and Plumbing Company of Douglas, GA Notice to Proceed December 17, 2007 Total project cost is $9.1 M EAST BEACH PROJECT STATUS
SCHEDULE • Preliminary Start of Construction Early January 2008 • Construction Period 18 Months • Estimated Completion June 2009
SERVICE LINE RESTORATION Homeowner Responsibility • Sanitary sewer service line installation on private property will be the responsibility of the homeowner • Water service line installation on private property will be the responsibility of the homeowner
SERVICE LINE RESTORATION Glynn County Responsibility • All water, sewer and drainage construction within the public rights-of-way and easements will be performed by Glynn County • New radio read water meters will be installed in the East Beach neighborhood
PUBLIC PROPERTY • Streets will be repaved • Contractor will seed all disturbed areas upon completion of work • Landscape plants will not be restored • Permanent structures on rights-of-way will not be restored • Walls, Brick Mailboxes, etc.
PRIVATE PROPERTY • Driveway restoration of paved driveways will be limited to plain concrete or asphalt • Irrigation systems in the rights–of-way will not be restored
COMMUNICATION • Letters to property owners • Door hangers • Glynn County website www.glynncounty.org • Verbal notification
COMMUNICATION • Public Meetings • CGL will be the primary point of contact during the construction phase for homeowners
PROGRAM MANAGER Travis Thomas Carter Goble Lee, LLC 1801 B Gloucester Street Brunswick, Georgia 31520 Office (912) 264-0357 Mobile (770) 560-1146 tthomas@leedesign.com GLYNN COUNTY ENGINEERING Jim Bruner, P.E. Engineering Department 700 Gloucester Street Brunswick, Georgia 31520 (912) 554-7495 jbruner@glynncounty-ga.gov GLYNN COUNTY ADMINISTRATION Becky Rowell 701 G StreetBrunswick, Georgia 31520 (912) 554-7171 browell@glynncounty-ga.gov www.glynncounty.org CIVIL ENGINEER Brennan Jones, P.E. Integrated Science & Engineering 105 McIntosh Crossing Fayetteville, Georgia 30214 (770) 461-4292 bjones@intse.com CONTACTS