70 likes | 169 Views
MICE VC 103. MICE Hall Chris Nelson. Hall Progress Highlights. Shielded area virtually complete SW corner Extra wall near Door and roof subject to survey Buffer tank and platform installed- Ready for Linde Q35 stands: All major parts in manufacture or delivered
E N D
MICE VC 103 MICE Hall Chris Nelson
Hall Progress Highlights • Shielded area virtually complete • SW corner • Extra wall near Door and roof subject to survey • Buffer tank and platform installed- Ready for Linde • Q35 stands: All major parts in manufacture or delivered • 2nd Q35 magnet within week of completion, but expected delay due to technician holidays • DS Extension frames at RAL, rails being added.