MICE VC 103. MICE Hall Chris Nelson. Hall Progress Highlights. Shielded area virtually complete SW corner Extra wall near Door and roof subject to survey Buffer tank and platform installed- Ready for Linde Q35 stands: All major parts in manufacture or delivered
E N D
MICE VC 103 MICE Hall Chris Nelson
Hall Progress Highlights • Shielded area virtually complete • SW corner • Extra wall near Door and roof subject to survey • Buffer tank and platform installed- Ready for Linde • Q35 stands: All major parts in manufacture or delivered • 2nd Q35 magnet within week of completion, but expected delay due to technician holidays • DS Extension frames at RAL, rails being added.