I-95 Accelerated Bridge Construction Project: PCUs, Method of Delivery, & Lessons Learned

I-95 Accelerated Bridge Construction Project: PCUs, Method of Delivery, & Lessons Learned. FHWA Peer Exchange Norfolk, VA February 28 , 2013. Scott J. Fisher, P.E. Jorge M. Suarez, P.E . Andrew Palahnuk. Project Background. Replace 11 bridges Richmond I-95 Corridor

gitano
Download Presentation

I-95 Accelerated Bridge Construction Project: PCUs, Method of Delivery, & Lessons Learned

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. I-95 Accelerated Bridge Construction Project: PCUs, Method of Delivery, & Lessons Learned FHWA Peer Exchange Norfolk, VA February 28, 2013 Scott J. Fisher, P.E. Jorge M. Suarez, P.E. Andrew Palahnuk

  2. Project Background • Replace 11 bridges • Richmond I-95 Corridor • Why ABC and not conventional? • 150,000 VPD • 234 PCUs

  3. Maintenance of Traffic (MOT) • Crossovers/Zipper barrier • Local traffic under bridge closures • VSP coordination • 8 pm - 6 am shift

  4. Casting Yard • 25-acre site • Mi-jack gantry cranes • Casting beds • Actual field substructure geometry • PCU storage

  5. Preconstructed Composite Units (PCUs) • LW concrete 9 inch slab • Fabricated plate girders • 2 or 3 girder components • Transverse PT bars • Cast-in-place closure pours • Continuity bars

  6. Existing Bridge Demo / PCU Erection

  7. Construction Challenges • Haul routes for PCUs / load ratings • 10 hour window for night work • Deploy zipper barrier • Sawcut deck • Remove demo pieces • Prepare beam seats • Set PCUs • Temp & final PT • Temp grid deck

  8. Construction Photos

  9. Lessons Learned • Allow for prep work prior to PCU replacement • Carefully review existing bridges for embedded expansion dams • Do not detail temp. grid deck design. Allow contractor to provide design • Avoid unreinforced “knife edges” for skewed bridges • Identify haul routes and bridge ratings • Eliminate anchor bolts (use restraint blocks)

  10. Lessons Learned • Maintenance/Repairs of existing structures during life of project • Consider slotted holes in diaphragm w/ friction connections • NEVER cut PT bars in the field w/o approval • CSX Railroad Constraints • Overhead Power Lines • Staging Areas • Final Grinding of PCUs

  11. Lessons Learned Cones make for great temporary supports!!!

  12. Acknowledgements • Owner: Virginia Department of Transportation (Richmond District) • CEI Consultant: Michael Baker Jr., Inc. • Engineer: URS Corporation • General Contractor: Archer Western Constructors, LLC

  13. I-95 Accelerated Bridge Construction Project: PCUs, Method of Delivery, & Lessons Learned FHWA Peer Exchange Norfolk, VA February 28, 2013 Scott J. Fisher, P.E. Jorge M. Suarez, P.E. Andrew Palahnuk