1 / 68

Project Delivery in a Public University Environment

Project Delivery in a Public University Environment. Presented by: Paul Sherwood Senior Director – Facilities Design and Construction The Ohio State University. Agenda. Office organizational model Project Management Concepts Programming and Planning Design Bidding and Construction

piper
Download Presentation

Project Delivery in a Public University Environment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Delivery in a Public University Environment Presented by: Paul Sherwood Senior Director – Facilities Design and Construction The Ohio State University

  2. Agenda • Office organizational model • Project Management Concepts • Programming and Planning • Design • Bidding and Construction • Project Closeout and Wrap-up

  3. Office Organizational Model 4

  4. Statute, Policy & Process Three distinct areas to be aware of: Statute (State Law) Policy (Established by the Board of Trustees) Process (Developed by the department to ensure an efficient process). 5

  5. Support Process #1 Support Process #2 Support Process #3 Support Process #4 1 2 3 4 5 High-level Process Sub Process A B C D E Benchmarking a1 a2 Tools a3 a4 Project Management Information System Project process “parts”

  6. Manage Deliverables Procure Services/ Products Close the Phase Close the Project Initiate the Project Plan the Project by Phase Perform Project Controls Manage Project Changes Project process flow

  7. Initiating a project Gain Alignment on Project Definition Close the phase, prepare for next phase Confirm Project Concept with Customer Receive Project Request (variety of means) Initial Project Setup (PM, funds and #)

  8. Initiate the Project Project is received through: Capital Request Process Basic Renovation Request Process Repair & Renovation Request Process Project Request Form Process 9

  9. Initiate the Project 10

  10. Initiate the Project 11

  11. Initiate the Project 12

  12. Initiate the Project 13

  13. Initiate the Project 14

  14. Chartering • Key Characteristics • Establish the project team • Define project purpose • Define roles and responsibilities • Establishing this is critical to success • Draft operating guidelines • Establish interpersonal behaviors • Prepare and sign chartering agreement

  15. Records Management • Consolidated project files with Accounting, Contracts, FDC, and PARE • One file folder template for consistent filing – can be modified to fit project size • Create a filing system that is user friendly and documents can be easily retrieved

  16. Records Management Layout

  17. File Structure Template • One template for both electronic and hard copy files • Template can also be used as checklist to validate documents have been put in file

  18. File Structure Template (cont’d) • Project folders begin with Project Number and then Project Name Ex: OSU-080100_Arps Hall – Suite 288 • Letters, memos, templates and tools are referenced under the appropriate folder

  19. Planning the Project Complete additional components of the work plan Develop scope and WBS by Phase Develop schedule and cost/budget information Gain Endorsement of the Work Plan

  20. Work Breakdown Structure (WBS) • Hierarchical list of tasks and subtasks • Criteria of a task / sub-task: • Definable beginning and end • Finite duration • Assignable level of effort • Status toward completion (% complete) • Reviewable deliverable at completion

  21. Affinity Diagramming to Build WBS WBS TITLE C(Sub-Category) TITLE B(Sub-Category) TITLE A(Sub-Category) AssignableWork AssignableWork AssignableWork AssignableWork AssignableWork AssignableWork AssignableWork AssignableWork AssignableWork

  22. The purpose of the project is to assess the degree of contamination at construction site Gather and Report Existing Data Conduct Field Investigation Prepare Final Report Gather and Review Data Prepare Baseline Memo Collect Field Samples QC Samples Collected Analyze Data from Samples Develop and Submit Final Report Small Project Example • Constructing a WBS • Define major categories of work • Determine assignable tasks for categories

  23. Sequence the Tasks ExcavateFoundation PlaceForms PlaceRebar PlaceConcrete CureConcrete START PlacePlumbing Frame WallComponents Install RoughElectrical Prepareto Move Lay RoofShingles Install RoofSheathing InstallHVAC InstallElectrical Frame RoofComponents

  24. Add Durations ExcavateFoundation PlaceForms 0.3 hr 0.3 hr PlaceRebar PlaceConcrete CureConcrete 0.3 hr START 0.3 hr 0.8 hr PlacePlumbing 0.5 hr Frame WallComponents Install RoughElectrical 0.5 hr 1 hr Prepareto Move Lay RoofShingles Install RoofSheathing 0.5 hr 0.1 hr 0.5 hr InstallHVAC InstallElectrical Frame RoofComponents 0.3 hr 0.7 hr 1 hr

  25. Project Scheduling Tool 26

  26. Project Scheduling Tool 27

  27. Jan. 1, '95 Jan. 8, '95 Jan. 15, '95 Jan. 22, '95 Task Name Dur. Start End ID M T W T F S S M T W T F S S M T W T F S S M T W T F S 1 1day 1/4/95 1/4/95 Create Project Workplan 2 Estimate materials 1day 1/5/95 1/5/95 Stake out 1day 1/6/95 1/6/95 3 4 1day 1/6/95 1/6/95 Excavation 5 1day 1/6/95 1/6/95 Order Materials 6 1day 1/6/95 1/6/95 Order Re-Bar 7 1day 1/6/95 1/6/95 Order Concrete 8 Order Lumber 1day 1/6/95 1/6/95 9 7 days 1/9/95 1/17/95 Complete Foundation 10 1day 1/9/95 1/9/95 Place Re-Bar 11 Set forms 1day 1/10/95 1/10/95 12 1day 1/11/95 1/11/95 Pour Concrete 13 3 days 1/12/95 1/16/95 Cure Concrete 14 Strip forms 1day 1/17/95 1/17/95 Gantt Chart Example

  28. Determine Critical Path • Minimum time needed to complete the project • One critical path for every project

  29. Calculate Float • The amount of delay that is possible without impacting the end date • You can have negative float and the job is late before it starts • Decide who gets the float and use it to allocate resources

  30. Initial Project Budget • Cost Estimator developed structure • PM’s will continue to do estimates • Consistent approach to development • Project data will be incorporated into our database for reference

  31. Workplan Components • Essential Elements of Workplan • WBS • Project Schedule • Project Resources • Project Budget • Project Specific Procedures • Quality Management Plan • Customer Service Plan • Change Management Plan • Closure Plan • Health and Safety • Records/Info Management Plan

  32. Procure Services Prepare and Place Ads Review/ evaluate Proposals, 0255’s/Bids Select/ Associate/ Contractor/ Vendor Obtain approval of contract (if necessary) Issue Contract/ Purchase Order Obtain Appropriate Authorization (e.g. BoT) Confirm funding sources

  33. Approve Deliverables Review/ Approve Payments/ invoices Manage Deliverables Review/ Evaluate Deliverables per Project Work Plan Kick-off/ Charter Core Project Team (w/provider) Distribute Deliverables to others for review Evaluate vs. Contract terms and Work Plan

  34. Perform Project Controls Update Percent Complete Reconcile Accounts Assess overall performance vs. project work plan Communicate status to customers Update Schedule Status Change Is Required Review Project Performance Update Percent Spent

  35. Manage Project Changes Develop Response to change with team Update Project Work Plan Evaluate potential change Obtain appropriate authorization Communicate change to stakeholders Modify/ Contract, PO

  36. Close the Phase Update/ archive Project Files for the phase Conduct final review of deliverables for the phase Obtain Endorsement of final deliverables from customer Perform/accept final actions (punchlist)

  37. Close the Project Perform Administrative and Financial Closeout Complete Project Assessment Conduct Lessons Learned Final update / archive of project files

  38. Closeout Plan • Closeout Plan should address • Roles and responsibilities • Review and obtain endorsement of final deliverables with customer • Update and archive project files • Perform financial and administrative closeout of the project • Document and disseminate lessons learned • Transition to Operations / Utilities / Customer

  39. Closeout Plan • Conduct project performance assessment • Quality • Customer Satisfaction • Cost & Schedule • Project Team Performance • Associate/Contractor Performance • Recognize successful performance on the project • Demobilize the project team and other resources

  40. Project Success Elements • Communication • Resource Management • Change Management • Project Tools • Support Processes

  41. Communication • Establishing Customer Relationships • Teams are dedicated to customer groups • Customer expectations • No surprises and no changes • PM to be available when needed • Unlimited flexibility • How to achieve customer satisfaction • Understand their needs • Clear, concise, consistent communication

  42. Communication Plan • Who to communicate with… • Customers & stakeholders • Other FOD “houses” • University departments • University community • When to communicate with them… • Early and often

  43. Communication Plan • How to communicate… • E-mail, newsletters, web, specific publications • What to say… • Critical information summarized based on the audience • Be careful of too much detail… the message gets lost. …repeat multiple times…

  44. Communication Plan • Example communication…

  45. Communication Plan • Elements to include: • Project information • Key contacts • Brief status • Meeting dates • When to expect the next update

  46. Communication Plan Purpose is to ensure that all team members, management, associates, contractors, customers, and stakeholders involved in the project provide and receive appropriate communications Communications should be clear and concise Consider the audience Summarizing v. detail “The right message at the right time.” 47

  47. Manage Resources • Staff Resources • What expertise will you need? • When will you need it? • How long will you need it? • What if the schedule changes? • Remember: Resources cost money…

  48. Manage Resources • Budget Resources • No one has an endless supply of funds for cost overruns • Remember you have ultimate accountability for the fiscal success of the project • “Holding” pay applications is illegal • They need to be paid or rejected in a timely manner

  49. Manage Resources • Space Resources • Coordinate staging areas with other projects and stakeholders • Project trailers are important, but not required on every project • Renovation work in fully occupied facilities has it’s own challenges…be sensitive to those • Plan well in advance for space you may need and communicate those needs

More Related