OP during LS1 Mike Lamont
24/7/365 as usual ELENA CONSOLADATION - LINAC4 - BOOSTERUPGRADE- HIE-ISOLDE- TSR - ACCOR - PS UPGRADE - CTF3 OP@LS1
BE-OP 2013 to 2014 • Technical infrastructure coverage • 2nd operator required at all times • Work on non-LHC projects • LINAC4, PSB upgrade, SPS upgrade, HIE-ISOLDE • Work on non-LHC consolidation • AD, PSB, PS, SPS • Shutdown coordination • Controls renovation • CTF3 operations OP@LS1
AD Largely dominated by AD consolidation and ELENA OP@LS1
LHC • Heavy involvement in consolidation • Have also to look forward to hardware commissioning OP@LS1
PS OP@LS1
PSB HIE-ISOLDE, Booster upgrade, LINAC4 commissioning, software OP@LS1
SPS OP@LS1
LHC consolidation OP@LS1
Requests LHC consolidation Fully covered OP@LS1
Requests R2E and support for Engineering for coordination OP@LS1
Requests QPS, LHC & SPS vacuum, LINAC4, Cabling, RF software, BI, CTF OP@LS1
RF software • Denis Cotte would be a good candidate to help with software for RF in the PS complex in LS1 - noted • YannickLe Borgne to work with Anthony on the SPS RF controls renovation as we already discussed. • Have discussed with Joao Carlos Oliveira he confirms that he is interested in working with us, during the LS1, on PLC projects. • It was already agreed, with K. Hanke, that Miguel Lozano will help for HIE-Isolde controls with D. Glenat OP@LS1
Cabling • At present there are two operators earmarked to work on cable supervision they are: • FabriceChapuis : • Mainly for any PSB cabling works, since he nows that machine very well. He might also be useful for any Linac4 works. • Pascal Fernier: • Mainly for ISOLDE (and HIE-Isolde) • The only issue here might concern the preparation of the cabling campaigns – if this needs to be done during the running period of 2012. Both will continue working on the operation of the machines until the beginning of LS1. • Isabelle Laugieralso now done for 50% cabling support (tbc) OP@LS1