400 likes | 610 Views
Project Monitoring and Control with EVA and Burn Graphs. Guy Davis Kendra Hamilton Ed Dantsiguer. Agenda. Origins of EVA EVA Explained EVA Examples Shortcomings of EVA Agile side of EVA Burn Graphs Tools Discussion. Overview of EVA.
E N D
Project Monitoring and Control with EVA and Burn Graphs Guy Davis Kendra Hamilton Ed Dantsiguer
Agenda • Origins of EVA • EVA Explained • EVA Examples • Shortcomings of EVA • Agile side of EVA • Burn Graphs • Tools • Discussion
Overview of EVA • “The essence of [Earned Value Management Systems] is that some level of detail appropriate for the degree of technical, schedule, and cost risk or uncertainty associated with the program, a target value ….is established.” Paul Solomon 2002.
History of EVA • PERT/Cost (1963) • DoD Cost/Schedule Control Systems Criteria (C/SCSC) (1967). • Government Performance and Results Act (1993), Federal Acquisition Streamlining Act, Title V (1994), Clinger-Cohen Act (1996) • EIA-748-1998 “Earned Value Management System” • Office of Management and Budget (Circular A-11, Part 7) (2003)
Motivation for EVA • Integrates work, cost, and schedule metrics. • Early warning signal. • Driving by looking in the front windshield instead of the rear view mirror. Statistical projection. • U.S. Government requirement.
Cost EarnedValue Schedule Technical Performance EVA Explained 1/3 • EVA concentrates on project management and control • Requires a number of tasks to be performed before utilizing EVA: • Work Breakdown Structure (WBS) • Creation of detailed plan (critical path plan) • Includes all activities that have to be performed, their durations, costs and relative contributions to the overall deliverable
EVA Explained 3/3 • EVA is used to determine current project performance and estimate/forecast future project performance • Based on 3 data points: • Budgeted Cost of Work Performed (BCWP) • Actual Cost of Work Performed (ACWP) • Budgeted Cost of Work Scheduled (BCWS)
Budgeted Cost of Work Performed • Planned (budgeted/estimated) cost of work that has been completed until this point • Answers: “How much was performed work supposed to cost?” • Based on features/activities completed and the budgeted amount for these features/activities in the original project plan
Actual Cost of Work Performed • Actual cost of work that has been completed until this point • Answers: “What was the actual cost of work actually performed?” • Based on features/activities completed and cost of these features/activities in real life
Budgeted Cost of Work Scheduled • Planned (budgeted/estimated) cost of work that was supposed to be completed • Answers: “How much work should have been done and how much was it meant to cost?” • Based on features/activities planned/scheduled and the budgeted amount for these features/activities in the original project plan • Budget at Completion (BAC) is the total funds allocated (budgeted) for this project to complete
Derived Metrics • Schedule Variance (SV) • SV = BCWP – BCWS • Compares what is done with what was supposed to be done • SV < 0 project is behind schedule • Cost Variance (CV) • CV = BCWP – ACWP • Compares actual project cost with budgeted project costs • CV < 0 project is over budget
Schedule/Cost Performance Index • Schedule Performance Index (SPI) • SPI = BCWP/BCWS • SPI < 1 project is behind schedule • Cost Performance Index (CPI) • CPI = BCWP/ACWP • CPI < 1 project is over budget • Cost Schedule Index (CSI) • CSI = CPI * SPI • CSI < 1 project is not tracking to plan • The further away CSI is from 1, the less likely is successful project recovery
Using EVA Metrics in Project Control 1/2 • Each individual EVA metric is not greatly useful on its own • Metrics need to be considered as a group • Ex: Just because a project has a CSI of 1 does not imply that the project is doing well – it may be well ahead of schedule while also being well ahead of its budget
Using EVA Metrics in Project Control 2/2 • ACWP metric can be used to project future activity costs/durations • This is called Estimate To Completion (ETC) • The end of the projected ETC curve is the Estimate At Completion (EAC) • estimated schedule and cost required to complete the project based on current productivity and spending • Comparison between EAC and BAC shows is the project is likely to be on schedule and/or on budget • Variance at Completion (VAC) schedule difference between BAC and EAC
Recommended Performance Metric Values Per the “U.S. Marine Corps Acquisition Procedures Handbook,” June 1997
EVA Task Types • Discrete Effort • Activities with start and end time that result in deliverables • Apportioned Effort • Effort required to support discrete effort tasks (Ex: inspections, quality control) • Proportional to the type/size of discrete effort tasks that they support • Level of Effort • Overhead activities with no concrete deliverables (Ex: management and administrative activities)
Crediting Earned Value • Discrete Effort • Credited upon completion with actual cost and duration tracked • Apportioned Effort • Credited upon completion of related discrete effort tasks • Level of Effort • Credited according to plan (regardless of actual cost and duration)
Crediting Earned Value Methods • Milestone Events • Weighted Milestone Gates • Percentage Complete • Fixed Formula • Level of Effort • Percentage Complete and Milestone Gates
EVA Example 1/2 • Planned/Scheduled Data: • Duration of 10 months • Includes 10 features with multiple tasks • Budget of $100 million • Actual After 6 Weeks: • 55% of the work has been completed • $85 million has been spent
Success Factors for EVA • Quality of the baseline; need to include all details. • Take action early based on performance indicators. “I hate everything that merely instructs me without augmenting or directly invigorating my activity” Goethe
Shortcomings of EVA • Based on past performance; assumes constant rate of spend and value creation • Assumes a direct relationship between time and cost. • Value measured in technical components, not expected business value. • Project must be fully defined at outset; the devil is in the details. • Time required for measuring project’s progress
EVA Tools • Excel • Welcom “Cobra” http://www.welcom.com/ • Schedulemaker http://www.schedulemaker.com • Planisware “OPX2” http://www.planisware.com/ • RiskTrak http://www.risktrak.com/index.htm • Winsight http://www.cs-solutions.com/ • Primavera Systems http://www.primavera.com/
EVA compared to Agile • Full project view vs. Iterative view • Tasks fully defined vs. Changing requirements • Attempts to forecast future vs. Determination of next iteration • EVA is not suitable for truly “Agile” projects
EVA in an Agile/Iterative Project • Approach 1: • Stories = BCWS • Tasks = BCWS in more detail • Assignments = ACWP • Velocity = BCWP • Testable requirements = 0% or 100% BCWP
EVA in an Agile/Iterative Project • Approach 2: • Do EVA on individual iterations • Approach 3: • Generate micro estimations for current iteration and macro estimations for future iterations
Burn Graphs • Origins of Burn Graphs • Cumulative flow diagrams from lean production • Goal: to provide a succinct view of progress. • Allows project sponsors to steer the project. • Allows scrum master report visually to stakeholders. • Allows the team to gain experience estimating by getting direct feedback. (Empowering)
Burn-Down Graphs • Shows remaining estimated effort on item • Usually in ideal engineering time (IET hours) • Calculated for any level of task abstraction
Scrum Backlog Graphs • Product Backlog Graph • High-level view of overall project progress. • Completion date: work left versus resources available. • Quantitative tool for making trade-offs. • Sprint Backlog Graph • Detailed view of a single sprint's progress. • Sprint signatures: compare current with past results. • First notice of schedule slips seen here.
Burn-up Graphs • Shows progress on completion of item • Usually displays percentage complete • Just the inverse of a burn-down graph
Cumulative Flow Diagrams • Tracks number of features (and status) over time • Better for reporting than: • % complete graph of feature milestone percentages • Features completed over time
Drawbacks Metric choice is key Over-simplification? Hides dependencies Should be able to zoom to see levels Traditionalists will resist implementation? Overview of Burn Graphs Benefits • Easy to compile/track • Feedback to the team and status to the customer • Highlights: • Schedule slips • Scope creep
Burn Graph Tools • Open-source • Outreach Project Tool (OPT) • XPlanner • Commercial • Version One • MS Excel
References • Anderson, David J. “Using Cumulative Flow Diagrams with FDD”. Feature Driven Development. 2003. http://www.featuredrivendevelopment.com/node/view/515 • Anderson, David J. Agile Management for Software Engineering. Prentice Hall. 2003 • Alleman, Glen B., Henderson, Michael, “Making Agile Development Work in a Government Contracting Environment” Proceedings of the Agile Development Conference, IEEE, 2003. • Fleming, Quentin W., Koppelman, Joel M., “Earned Value Project Management: A Powerful Tool for Software Projects”, Crosstalk, July 1998. • Hayes, Heather, “Using Earned-Value Analysis to Better Manage Projects”, Pharmaceutical Technology, February 2002. • Howes, Rodney “Improving the Performance of Earned Value Analysis as a Construction Project Management Tool”, Engineering, Construction and Architectural Management, 2000. • Schwaber, Ken and Mike Beedle. Agile Software Development with Scrum. Prentice Hall. Upper Saddle River, NJ. 2002 • Solomon, Paul J., “Practical Software Measurement, Performance-Based Earned Value,” Crosstalk, September, 2002.
Discussion Points • Can EVA be applied to agile projects? • What metrics would you use for burn graphs? • Would you adopt burn graphs at your organization?