Water & Wastewater Capital Charges Discussion Agenda July 14, 2009
Capital Charges • Background • Methodology • 2008 Update • Other Utilities – Comparison • Next Steps
Background • Capital Charges • Paid by developers for infrastructure to serve growth • Mechanism for growth to “pay its own way” • Used only for growth related projects
Background • Capital Charges • Discretionary source of funding • Cannot exceed full cost recovery • Can be set below full cost recovery
Background • Current Charges • Based on 2004 study • Phased in over time • Set at full cost recovery • Considered future alternative water infrastructure
Background • Current Charges • Water • $1,950 per ERC • 350 GPD • Wastewater • $3,668 per ERU • 300 GPD
Capital Charges • Background • Methodology • 2008 Update • Other Utilities – Comparison • Next Steps
Methodology • Combined Cost Basis Approach • Replacement cost of existing system infrastructure • Future capital improvements cost to develop future system capacity • Costs are brought to present value • Credit applied to remove Debt Service costs funded from rates
Capital Charges • Background • Methodology • 2008 Update • Other Utilities – Comparison • Next Steps
2008 Update • Assumes groundwater and alternative water as sources of supply • 5 year planning horizon used for groundwater • 10 year planning horizon used for alternative water
2008 Update Water Current $1,950 Update $2,603 +$ 653 33.5% Wastewater Current $3,668 Update $3,673 +$ 5 0.1% Combined Current $5,618 Update $6,276 +$ 658 11.7%
Capital Charges • Background • Methodology • 2008 Update • Other Utilities – Comparison • Next Steps
Capital Charges • Background • Methodology • 2008 update • Other Utilities – Comparison • Next Steps
Next Steps • BCC Direction • Option A: • Proceed with DAB and LPA review • Conduct Public Hearing with BCC • Adopt updated charges • Option B: • Delay updated charges • Maintain existing Capital Charges at current levels • Update the report in two years
Water & Wastewater Capital Charges Discussion Agenda July 14, 2009