On behalf of everyone involved A brief snapshot of first B2 dump commissioning

On behalf of everyone involved A brief snapshot of first B2 dump commissioning. LBDS B2 initial commissioning. Had about 140 shots on TDE altogether 116 shots initially extracted with corrector knob “ONE_MKD_CORRECTORS” Vertical position ~120 mm too high on BTVDD

gunda
Download Presentation

On behalf of everyone involved A brief snapshot of first B2 dump commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. On behalf of everyone involved A brief snapshot of first B2 dump commissioning

  2. LBDS B2 initial commissioning • Had about 140 shots on TDE altogether • 116 shots initially extracted with corrector knob “ONE_MKD_CORRECTORS” • Vertical position ~120 mm too high on BTVDD • MSD strength error understood (2.6 mrad cf 2.4 mrad). Access to UA63/67 to modify BETS tables when confirmed with beam • Losses at exit of MSDC – poor H/V trajectory with large beam • 18 shots with MKD and MKBs on, with big vertical bump (70 urad) • Correctly extracted Looks good so far – but no detailed measurements made • Aperture of extraction channel, basic timing in, MKD/B sweep shape

  3. BTVSE BI generally looking good • BTVs – double trigger when kickers firing – still seemed to miss some acquisitions? • BLMs – looked good – logging problems • BPMSE OK, BPMD not logged • BCT – needs work still BTVD BTVDD

  4. Losses and trajectories • Plenty of losses seen during whole period • Losses every shot on TCDS • BTVSE with Al? Check by taking this out next time • Steered to avoid losses on MSDC and MKBs

  5. Other observations • Had one shot onto the TCDQ • 2nd manual I&D – not quick enough to re-enable the LBDS I&D • 1 bunch through the MSDs to TCDQ • Saw clearly on loss logging • No trajectory data found for this shot  • YASP autosave ON by default during these days?

  6. Initial trajectory • Reconstructed from screen data: started with +2.4 mm and -35 urad at Q5. • Trimmed down as much as possible (70 urad) at 07:10 on 6/08

  7. Outline of LBDS stuff still to do… • Still some tests without beam to make • 450 GeV checks of 45 connection (ongoing) • Energy tracking with 4 sectors connected (several ramps – can parasite) • I&D sequence & timing for B1 • Beam tests • Need trajectory and optics moderately well sorted • Do the basics for B1 • Then plough into measurement programme… • 2-3 shifts with present conditions • Start tonight with B2? • Need to make sure no beam into 56… • Concerns about not rocking the boat on J-1….