An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HOSPITAL PENAWAR DEVELOPMENT & IMPROVEMENT 07.12.2011

  2. NOT UPDATE IN FORUM MAINTENANCE SEPTEMBER REPORTING - RESOLVE 90% WALL PAPER RESTORATION MyCard & MEDILINK NEW GENERAL X-RAY RENOVATION COMPLETION HP STAFF COMPETENT CHART

  3. ROOM 201 REFURBISHMENT

  4. 1.WALLPAPER TIDAK MENCUKUPI (TUNGGU DARI SUPPLIER)2.SKIRTING SEDANG DI VARNISH3.CURTAIN DAH PASANG

  5. LIFT B IMPROVEMENT

  6. Kayu-kayu sedang di varnish dan target pemasangan pada RABU (7/12).

  7. WEEKLY OPS SUCI

  8. Training Ops Suci - preparation of 2 days program before proceed with program.Checklist for Ops Suci - Done on 26 Nov 2011 and 3 Dec 2011 (Saturday).

  9. NEUROSURGERY

  10. EQUIPMENT • MICRO BURR ~ DONE

  11. TRAINING • Visit HSA Neurosurgery department by Friday - 10.00 am • Tentative program will be discuss with Matron Hasmah upon visit.

  12. NEW EQUIPMENT

  13. ENT EQUIPMENT • LAST WEEK PROGRESS1 - LIGHT SOURCE   - MODEL U9112GL  350-5A    - PRICE USD 8702 - CAMERA SYSTEM   - MODEL U9226F-168D   - PRICE USD 4300ACTIVITY PROGRESS- waiting for TT progress & payment

  14. CCTV

  15. CCTV installation - donePROBLEMCurrently, use 2 unit of DVR (16 channel) - old and new.Old DVR keep restating - send for repair. Temporary, replace by old DVR (4 channel)

  16. PENAWAR BUS

  17. SPAD start to process our application on Tuesday, 6 December 2011.They need some supporting document which is:1) current bank statement (MBB & Bank Islam)2) Bus picture3) Revenue / liability / asset value of the companyI already sent the supporting document to them by email on 6 December 2011.

  18. PARADE IMPROVEMENT

  19. Upgrade parking lot - waiting from D&E

  20. SMART PHONE /BLACKBERRY HODs - FULL APPLICATION

  21. This week audit on 8 December 2011

  22. PENAWAR LANDSCAP CORNER

  23. MINGGU 1: DATE: 31/11/2011 - 6/12/2011ACTIVITY:1. PENERIMAAN PROJEK, LAWATAN TAPAK PROJEK, PERBINCANGAN BERSAMA ANTARA JABATAN MP & PR (EN DIN)2.  PERBINCANGAN PELAN PEMBANGUNAN PROJEK.3. DRAWING KAWASAN DAN ILUSTRASI KAWASAN PROJEK TERSEBUTMINGGU 2DATE: 7/12/2011 - 13/11/2011AKTIVITI:1. PRESENT PELAN CADANGAN PROJEK KEPADA PENGURUSAN2. MENJALANKAN KERJA MENYANGKUL TAPAK KAWASAN.3. PROSES MERATAKAN TANAH DAN MEMBUANG RUMPUT ASING PADA KAWASAN TERSEBUT4. PRESENT PERKEMBANGAN AKTIVITI PROJEK

  24. MINGGU 3DATE: 14/11/2011 - 20/11/2011AKTIIVITI:1.  PRESENT PERKEMBANGAN PROJEK2.  PERBINCANGAN PELAN DENGAN PIHAK PENGURUSAN3.  AKTIVITI MENYANGKUL DAN MEMBERSIHKAN KAWASAN SEDANG GIAT BERJALANMINGGU 4DATE: 21/11/2011 - 27/11/2011AKTIVITI:1. PRESENT PERKEMBANGAN AKTIVITI2. AKTIVITI MENYANGKUL SEDANG GIAT DIJALANKAN3.  PEMBELIAN RUMPUT DAN MENAMPAL RUMPUT (FASA PERTAMA)4.  4O KEPING RUMPUT TELAH DIBELI PADA HARGA RM 400.00

  25. MINGGU 5DATE: 28/11/2011 -  4/12/20111. PRESENT PERKEMBANGAN PROJECT2. AKTIVITI MENYANGKUL SEDANG BERSAMBUNG LAGI3. PEMBELIAN RUMPUT UNTUK FASA 2 SEBANYAK 50 KEPING PADA HARGA RM 5004. PENAMPALAN RUMPUT DIJALANKAN.5. PENGALIHAN POKOK LAMA YANG TERDAPAT PADA KAWASAN TERSEBUT DILAKUKAN

  26. PROGRESS TERKINISTATUS: 50% TELAH SIAP

  27. GAZEBO

  28. STATUS: ON PROGRESSDATE: 29/11/2011 - 5/12/2011PROGRESS:1. 2 UNIT TELAH SELESAI DIPERBAIKI KEROSAKAN PADA BAHAGIAN STRUKTUR2. TELAH DIHANTAR KE KEDAI KANVAS UNTUK DIUKUR CANVAS TERSEBUT.SUPPLIER: KZ KANVASTEMPAT: PASIR GUDANGMATERIAL : HIGH QUALITY CANVAS PVCWARNA; MAROONHARGA: RM 750 / UNIT KUANTITI: 2 UNITJUMLAH: RM 1500.00

  29. PROGRESS TERKINI:DATE: 5/12/2011 - 11/12/2011STATUS: CANVAS TELAH DIPEROLEHI OLEH SUPPLIER, SUPPLIER MEMBERITAHU AKAN SIAP PADA HARI RABU 7/12/2011.INSTALLATION ON: 8/12/2011

  30. MOTORBIKE PARKING DESIGN & MX

  31. Saiful dan AP akan melaksanakan kerja perancangan dan pemasangan besi- mereka telah bermula semalam, 1 dis :                        - perancangan ke atas lokasi                        - penggunaan besi yang optima @ menggunakan besi yang sedia ada di bengkel                         - penggunaan bahan tambahan seperti cat anti karat dan cat luaran- dateline yang ditetapkan adalah pada hari rabu, 7 dis 2011

  32. NEW TRANSIT ROOM 100% COMPLETION

  33. 1) pemasangan skirting kayu di siling dan lantai2) pembelian fomeca untuk transit ward 2

  34. TRANSIT WARD 3 - LOBBY IMPROVEMENT

  35. 2hb Dec - Ibrahim telah memasang sebanyak 8 lampu tambahan downlight di lobby pada setiap aras transit ward lobby

  36. HEALTHY WORK POLICY FOR STAFF

  37. 1. Category :1. Pre employment2. Annual medical check up for staff male/female 35 years and above and more 5 years services3. Annual medical check up for staff male/female below 35 years and more 5 years services2. Flow Chart as per attached

  38. FLOW CHART Identify type of test Identify staff Issue memo/letter to staff Assessment Report send to HR Awareness Program Fit Analyze Report Rehabilitation Program Un fit

  39. DIALYSIS : KKM LICENSE SUBMISSION

  40.  To submit application form to National Kidney Foundation regarding Post Basic Haemodialysis • Staff to be send : SRN Che Hafizzuddin • Query from NKF : SRN Che Hafizzudin no experience in Dialysis 

  41. PEN 5 TRAINING

  42. Training & Program Basic Keyboard November Vocal Class December Guitar Basic January Basic Drum February Art and Performance March

  43. November progress(Basic Keyboard) Done

  44. Next Program Vocal Class (December 2011) Date Training, every Wednesday in December (7, 14,21,28 Dec 2011) Time 12.00pm to 2.00pm

  45. Senarai Nama

  46. DESARU ROAD SIGNAGE

  47. HP Signage yet to be installed (contoh as the following photo): Latest follow-up with Proline Road Marking (6/12/2011) - to install by Friday 9/12/2011.

  48. PHOTO GALLERY

  49. 24 Photos printed in Black & White.