1 / 10

Outsourcing Modifications To Contractors

Outsourcing Modifications To Contractors. Tom White Entergy – Pilgrim Station. June 29, 2009. Increased Use of Outsourced Engineers. Many staffs have “downsized” Experienced engineers have retired Specific technical skill sets have been lost

gwenllian
Download Presentation

Outsourcing Modifications To Contractors

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Outsourcing Modifications To Contractors Tom White Entergy – Pilgrim Station June 29, 2009

  2. Increased Use of Outsourced Engineers • Many staffs have “downsized” • Experienced engineers have retired • Specific technical skill sets have been lost • Large projects continue to emerge (e.g. power uprates, new plants, dry cask storage, security improvements)

  3. Outsourcing Options • All work done remotely under contractor programs (QA/non-QA) – Owner Review • Staff Augmentation – Contract engineers work at station under station’s programs • Other?

  4. Issues/Considerations • ESP training • Procedures (station vs. contractor) • Technical reviews by station • Oversight of productivity • Database access & update • Information access • Fixed cost vs. T&M • Teamwork

  5. Work Remotely Using Contractor Programs (with Owner Review) Pros • No ESP training oversight burdens (i.e. maintaining qualifications, mentoring/co-signing) • No paperwork burdens if contractor uses station procedures under their programs • Owner’s Review is only requirement • Contracts more amenable to fixed pricing Cons • Contractors not on-site so productivity must requires additional management (can be addressed by fixed price vs. T&M, periodic schedule reviews, etc.) • Station database access & update more difficult from remote location/server • Information access (walkdowns, drawings) more difficult • Teamwork requires more effort (to assemble meetings, resolve difficult issues face-to-face, etc.)

  6. Staff Augmentation Pros • On-site contractors can be managed directly for productivity • Station databases readily available for access & update. Contractor questions easily resolved • Access to information/drawings via walkdowns and document control centers is simple • Teamwork more easily promoted via timely face-to-face meetings • All products developed per station procedures Cons • Contractors have to be directly supervised by station • Significant ESP training oversight burdens (i.e. maintaining qualifications, mentoring/co-signing) • Substantial station technical reviews required until contractor qualifications are completed • Contracts are typically T&M which can be more expensive

  7. Implications for Configuration Management • Do the contractors fully understand your document control systems, document indexes, and information management systems? • Remote access availability and speed • Quality of document cross references and links (identifying impacted documents & programs) • Idiosyncrasies of legacy data in databases • Centralization of design basis information • Tribal knowledge of system engineers, Operations, etc.

  8. Implications for Configuration Management • Do the contractors thoroughly understand your document change procedures and electronic processes? • Identification of applicable design criteria • Methods for revising/creating each document type • Roles & responsibilities for each part of overall modification process • Quality training in the use of complicated workflow programs • Data entry quality & verification (e.g. BOMs)

  9. Summary/Recommendations • Continued high modification workload will require continued use of contractors • Build time & funding into contracts to address training in use of key databases and work management processes/procedures • Use graded approach to oversight of technical and configuration management tasks • Recognize limitations and pitfalls of your systems and assure contractors are aware • Verify station personnel are cognizant of goals of Owner’s Review versus technical HU reviews • Ensure regular communication between contractor and station POC • Consider steady flow of work to same contract personnel

  10. Questions?

More Related