World Bank Energy Forum. Benchmarking Objectives & Practices as Applied by NRECA International. Daniel Waddle NRECA International March 8, 2006. Benchmarking Methodology . Compare performance of the target utility to that of other organizations or to fixed standards.
E N D
World Bank Energy Forum Benchmarking Objectives & Practices as Applied by NRECA International Daniel Waddle NRECA International March 8, 2006
Benchmarking Methodology • Compare performance of the target utility to that of other organizations or to fixed standards. • Analyze gaps in performance to understand root causes of problems. • Explore options for improving performance. • Execute changes that will result in improved performance. • Measure outcomes and repeat process of identification, evaluation, and execution.
Benchmarking: In Best of Cases, a Three Step Process • Phase1 : Statistical review using data base of performance indicators • Phase 2 : Comparison of performance against “Best Practices” within peer group • Phase 3 : Implementing changes • NRECA’s experience in developing countries is that the first step is a significant challenge, and steps 2 & 3 may only come much later.
NRECA experience in benchmarking programs in many developing countries • Data collection, information organization, and data availability is quite problematic. • Utility information systems are often non-existent or poorly designed, and do not yield the data required to measure performance. • Utility staff often do not understand the value of data, how it can be used, and which data fields are important. • When data does exist, it is often poorly archived. • The first and often most difficult step in the benchmarking process is secure reliable data at all levels of utility operation.
RUS Form 7: Monitoring Rural Utility Performance with Monthly Data • Data collection template designed to facilitate financial, technical, and operational performance analysis • Originally intended to allow RUS to ascertain credit worthiness of U.S. cooperatives as borrowers to RUS loan fund • Includes multiple sections such as: • Statement of Operations: Expense/revenue summary • Changes in GT&D plant: new services, lines, transformers, etc. • Balance sheet: statement of assets & liabilities. • Employee statistics. • Statement of bulk power purchases & sales. • Power requirements data base: energy sales by consumer category
REB 550 Data Base • Derived from RUS Form 7 • PBSs submit monthly 550 reports to REB, REB processes data to evaluate performance • June 550 report summarizes annual statistics. • Electronic records date back to 1991. Hard copies are available to the early 1980s.
How does REB use the Form 550? • Monitors many performance indices, but a few are much more important than others: • Collection rate • Overall losses • Consumer data, including connections, sales, disconnections, etc. • Less emphasis on: • Tariffs • Power quality • Outages
How does REB use the data? • Each month, key performance indicators are summarized in a MIS report circulated to all REB senior officers. • Each year, REB officers meet with PBS management to review performance based upon the 550 data • Performance plans from the prior year are reviewed • Bonuses for all PBS managers are based upon targets set and achieved/not achieved • Performance targets are set for the following year • Targets are primarily set for levels of losses, collections, and new service connections
Statistical Analysis Using Historic Information Only Goes So Far • To determine causes of performance gaps, must evaluate causes in depth within target utility • Need to share information from better managed utilities with lower performing utilities • In Bangladesh, the medium through which this is done is REB – much experience in doing so • In other countries, can be facilitated by a peer group leader, such as consulting firm or utility organization • Without best practice studies, evaluating practices, and sharing experience, benchmarking programs have limited value.
While no two utilities are equal, there are common targets that should be achieved: • Collection rates: +90% • System losses: less than 12% • Cost of purchase power: more than 60% of total costs for grid connected systems. • Annual outage duration/consumer: less than 30 hours • Cost of new overhead primary construction: less than $12,000/km • Penetration rates in excess of 40% of potential clients