1 / 28

Super KEKB/Belle

Super KEKB/Belle. Toru Iijima Nagoya University December 6, 2008 New Hadrons with Various Flavors. Talk Outline. KEKB & Belle Super KEKB & Belle Physics target KEKB upgrade Belle upgrade Plan / New Collaboration Summary. Belle detector. Ares RF cavity. e + source. KEKB & Belle.

hansel
Download Presentation

Super KEKB/Belle

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Super KEKB/Belle Toru Iijima Nagoya University December 6, 2008 New Hadrons with Various Flavors

  2. Talk Outline • KEKB & Belle • Super KEKB & Belle • Physics target • KEKB upgrade • Belle upgrade • Plan / New Collaboration • Summary

  3. Belle detector Ares RF cavity e+ source KEKB & Belle • e- (8.0GeV) × e+ (3.5GeV) • ⇒U(4S) →BB • ⇒Lorentz boost: bg = 0.425 • Finite crossing angle • - 11mrad ×2 • Operation since 1999. SCC RF(HER) ARES(LER) Peak luminosity 1.71 x 1034 cm-2s-1 ! The World Highest Luminosity

  4. KEKB Performance Luminosity Records; • L peak = 1.71x1034cm-2s-170% higher than the design • L day = 1232pb-1/day double the design • L int = 855 fb-1as of Oct.28, 2008 KEKB/Belle: 709.9 fb-1 U(4S): 620.6 fb-1 U(5S): 21.2 fb-1 U(3S): 2.9 fb-1 Off-peak: 58.9 fb-1 The power of Continuous Injection Lum / day 1034 • Total:853 fb-1 • U(4S): ~740 fb-1 • U(5S): 23.6 fb-1 • U(3S)/U(1S) 2.9 / 5.7fb- • Off-peak: ~85 fb-1 The best day > 1.2 /fb

  5. B0J/yKS Achievement of the B Factories Quantitative confirmation of the KM model Confirmation of Kobayashi-Maskawa model Belle, July 05 B0J/yKS WA, PDG08 Discovery of CP violation in BB system Af ~ 0 Sf = 0.652±0.039±0.020 Belle, July 05 Violation of CP symmetry !

  6. B0J/yKS Achievement of the B Factories Quantitative confirmation of the KM model Confirmation of Kobayashi-Maskawa model Belle, July 05 B0J/yKS WA, PDG08 Discovery of CP violation in BB system The next challenge is to find what KM cannot explain ! It requires >1010 B and t pairs ! Af ~ 0 Sf = 0.652±0.039±0.020 Belle, July 05 Violation of CP symmetry ! Press release from the Academy “As late as 2001, the two particle detectors BaBar at Stanford, USA and Belle at Tsukuba, Japan, both detected broken symmetries independently of each other. The results were exactly as Kobayashi and Maskawa had predicted almost three decades earlier. “

  7. Physics Reach at Super-KEKB/Belle Upper limits Search for H± in B→tn 50ab-1 assume 5s discovery CP asymmetry in B→KKK, fK and h’K ■   ●      ★ 0.3 X10-9 (3s discovery lim.) 0.1 Deviation from SM Present exp. limits 0.03 CKM at 50ab-1 Integ. Lum.( ab-1) 5ab-1 Reach of B factories 50ab-1 0.01 Upgraded KEKB 1 10 100 Physics at Super B Factory (hep-ex/0406071) being updated. Integ. luminosity (ab-1)

  8. From Hadron Physics Point of View Discoveries of new resonances at Belle Y(4660) Y(4008) Z(4430) DsJ(2860) Integrated luminosity (fb-1) DsJ(2700) Xcx(3090) Y(4320) cc2’ X(3940), Y(3940) Y(4260) Sc* baryon triplet X(3872) D0*0& D1*0 Tau decays is also unique tool to study QCD. DsJ(2317/2460) hc’ & e+e-cccc • Study of detailed properties; JPC, production & decay. • More states; • Decaying to cc and K • ss counter-part • bb counter-part by quick energy scan.

  9. Super-KEKB Strategy Three factors that determine luminosity Beam-beam parameter: 0.059 (KEKB) → >0.24 (SuperKEKB) Stored current: 1.7 / 1.4 A (e+/ e- KEKB) → 9.4 /4.1 A (SuperKEKB) Lorentz factor Geometrical reduction factors due to crossing angle and hour-glass effect Classical electron radius Beam size ratio Vertical b at the IP: 6.5 / 5.9 mm (KEKB) → 3.0 / 3.0 mm (SuperKEKB) Luminosity: 0.17 ×1035 cm-2s-1 (KEKB) 5×1035 cm-2s-1 (SuperKEKB)

  10. Crab crossing New IR b*y = σz = 3 mm SuperKEKB Crab cavities installed and undergoing testing in beam e+ 9.4 A e- 4.1 A Dampiing ring The superconducting cavities will be upgraded to absorb more higher-order mode power up to 50 kW. The state-of-art ARES copper cavities will be upgraded with higher energy storage ratio to support higher current. Higher current More RF New vacuum system + Linac upgrade The beam pipes and all vacuum components will be replaced with higher-current design. will reach 8 × 1035 cm-2s-1

  11. Major components: Cost & Effects Items are interrelated. • Tunnel already exists. • Most of the components (magnets, klystrons, etc.) • will be re-used.

  12. Vacuum System • High currents (9.4/4.1A) & short bunch (sz=3mm) lead to; • Intense SR power • Max. power density of 28kW/m (40W/mm2) even at half aperture. • High Photon density • ~1x1019 photons/m/s in average. • Intense HOM power • For a loss factor of 1V/pC, loss power is ~200kW. Pump Beam SR • Copper beam duct w/ ante-chamber • TiN coating on inner surface • to decrease secondary electron • yield (SEY); max.SEY~0.9 • Clearing electrode • A possible measure even inside • of magnets f 90 mm

  13. Interaction Region q=17° q=150° SuperKEKB • Move final focus quad. closer to IP for lower beta functions at IP. • Preserve current machine- detector boundary. • Rotate LER 8 mrad. Crossing angle: 22-> 30 mrad • QCS and solenoid compensation magnets overlap in SuperKEKB. ESR-1 QCSL ESL-1 ESR-2 QCSR ESL-2 KEKB EFC QCSR QCSL ESR ESL Issues Causes Physical aperture around IP Lower b at IP Dynamic aperture Lower b at IP Detector background Higher beam current Heating of IP components Higher beam current & shorter bunch length Damping Ring

  14. RF Systems • Adopt the same RF frequency as KEKB and use the existing RF system as much as possible, with improvements as necessary to meet the requirements for SuperKEKB. Construction cost is greatly reduced. Technical uncertainties are relatively small. ARES Normal conducting cavity Superconducting cavity Normal-conducting ARES cavity: LER + HER Passive stabilization with huge stored energy. T. Kageyama et al. Superconducting cavity: HER S. Mitsunobu et al.

  15. High Power RF R&D • Normal Conducting cavities (ARES): • Upgrade of ARES with higher energy storage ratio. (left) • High power rf input couplers. • SiC dummy load with higher power capability (right). • Superconducting cavities: • The expected power load to the HOM absorber is 50 kW/cavity at 4.1 A, (even) with a larger beam pipe of 220 mmφ. • HOM damper upgrade may be needed.

  16. 22 mrad. crossing crab crossing Crab Crossing at KEKB • Crab Crossing can boost the beam-beam parameter > 0.15 . The squashed cell shape cavity studied by K. Akai in 1991 and 1992 under KEK-Cornell collaboration. Head-on (crab) Crab Cavity & Coaxial Coupler in Cryomodule K. Hosoyama et al. Crossing angle 22 mrad (Simulation:K. Ohmi)

  17. Test of Crab Crossing • Two crab cavities were installed in KEKB in January 2007. HER(8GeV e-) LER(3.5GeV e+) one for each ring • Beams have been indeed tilted ! outside of the rings inside of the rings Observation with streak cameras (H. Ikeda et al, PAC07 FRPMN035) longitudinal LER HER horizontal

  18. Specific Luminosity With Crab Crossing • Crab Crossing • 49 sp. βx*=80, 84cm the highest vertical beam-beam tune shift was about 0.088. • A number of measurements indicate effective head-on collision. • The vertical tune shift went from 0.055 to 0.088. • The specific luminosity/bunch improved by more than just the geometrical gain, by about 15%. • Need more time to achieve the goal (X2 specific luminosity). Simulation head-on before crab, tune shift was 0.055 3.06 bucket spacing Simulation 22 mrad 22 mrad crossing

  19. Super-Belle Strategy Issues 4Higher background ( 20) 4Higher event rate ( 10) 4Require special features • radiation damage and occupancy • fake hits and pile-up noise in the EM - higher rate trigger, DAQ and computing • low pm identification f smm recon. eff. • hermeticity fn “reconstruction” Possible solution: 4Replace inner layers of the vertex detector with a silicon striplet/pixel detector. 4Replace inner part of the central tracker with a silicon strip detector. 4Better particle identification device 4Replace endcap calorimeter by pure CsI. 4Faster readout electronics and computing system.

  20. Super-Belle (Baseline) ECL Wave sampling + pure CsI crystal(endcap) PID Threshold Aerogel + TOF → TOP + Aerogel-RICH KL/m detection RPC → Scintillator +SiPM(endcap) CDC Super small cell Longer lever arm New Dead time free readout and high speed computing systems SVD 4-lyr DSSD → 6lyr DSSD (option: striplet / pixel )

  21. Background Effects “sBelle Detector Study Report” posted as arXiv: 0810.4084 • Effective background with new hardwares New (*) Software efforts needed for CDC • Background effects on tracking Gain in reconstruction efficiency of BgD*D*(D*→Dps, D→K3p) We know how to handle the background.

  22. KEK Roadmap • KEK’s 5-year roadmap. • 3-year shutdown for KEKB upgrade • 0.5-1 year delay, KEKB will run in FY2009 • KEK management in close contact with MEXT. • “Investigation money” requested in FY2008. Hope Positive effects from the Nobel Prize …

  23. Luminosity Prospect 50ab-1 by ~2020 X50 present Results from LHC(b) Situation of LC… L~8x1035 cm-2s-1 10ab-1 (10x present) 3year shutdown for upgrade

  24. New collaboration • Super-Belle will be a new international collab. • Two proto-collaboration meetings in Mar&Jul, 2008 • Participation of new people from Germany, India, U.S., Japan,… . • Kick-off of the new collaboration: Dec.10-12, 2008. • Still many sessions will be open. • Near-term plan (preliminary) • Detector study report has been completed. • Detector proposals (by summer 2009). • The final detector design by Dec. 2009. Super-Belle webpage http://superb.kek.jp/ ML subscription is available. 2009 2010 2008 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 10 11 12 KEKB operation Internal review Detector proposals Kick-off meeting (Dec 08) TDR Actions to invite new collaborators

  25. Summary • KEKB/Belle has been running successfully, and brought important scientific and technical achievements. • Next generation e+e-B factory with L~1036 will be very useful to study the new sources of flavor mixing and CP violation. • It must be very interesting also from hadron physics point of view. • Super-KEKB: the target luminosity is 8 x 1035cm-2s-1, based on existing or tested technologies (mostly), which enables us to accumulate 10ab-1 by 2016, and 50ab-1 by 2020. • Super-Belle: detector upgrade studies are in progress, and will be finalized in 2009. • New collaboration is being formed; the kick-off meeting on Dec.10-12 at KEK (many sessions will be open). We are trying to get ready soon. Stay Tuned !

  26. Backup

  27. Linac Upgrade Pulse beam kicker for quick beam switching (50 Hz). Start testing this Fall Intensity Upgrades e+: stronger focusing field in capture section after target. e-: increase bunch current from pre- injector • Energy Upgrade (Positrons) • Replace S-band (2856 MHz) with • C-band (5712 MHz) RF system to double field gradient in downstream section of linac. • C-band linac: • completed a single section in the linac with 4 structures • Performance was satisfactory with beam.

  28. J-ARC e+ production e- gun BT e+ Damping Ring Damping Ring • Positron emittance needs to be damped, to pass reduced aperture of C-Band section and to meet IR dynamic aperture restrictions. • Electron DR may also be considered later to reduce injection backgrounds in physics detector, but for now only positron DR considered. • Damping ring located downstream of positron target, before C-Band accelerating section.

More Related