Improved Reliability through PM Optimisation

This project aims to improve reliability by optimizing preventive maintenance schedules and increasing the quality of maintenance. The objectives include better managing Cell C operation and maintenance, understanding equipment failure history, improving detection and rectification of failures, and communicating findings.

harnden
Download Presentation

Improved Reliability through PM Optimisation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Improved Reliability through PM Optimisation Project Team: Electrician Planner Mechanic Operator Reliability Engineer Facilitator: Steve Turner

  2. Why investigate the Residue Cell C’s • PM Optimisation will fall in line with the business plan for the Site. • The only cost centre in the plant consistently over budget. • Opportunity to improve reliability as Cell C’s have highest failure rate in the area. • Opportunity for more consistent performance to meet plant expansion plans. • The experience is that there is more work in the area than there are people assigned.

  3. Objectives • Better focus of PM schedules. • Increase the quality of maintenance. • Understand the rationale behind each PM task. • To better manage the Cell C operation and maintenance. • Exchange information and increase understanding of each role ie mech ,elect, process. • Understand equipment failure history. • Improve detection and rectification of failures. • Communicate findings.

  4. Objectives…cont • All of the previous will result in greater abilityfor us to meet the business plan.

  5. How we went about it • Started with the existing PM lists • Applied the process to the all schedules including: • SAP schedules • Maintenance and Process task lists • Check sheets • Created a new daily schedule for both operator and maintenance technicians. • Review failure modes and the PM’s which addressed these.

  6. How we went about it….con’t • Review operating logsheets • Determined the most appropriate maintenance strategy. • What task (preventive, predictive or corrective) • Who does it • How often. • Develop implementation list/plan for approval.

  7. Opportunities identified • Numerous new PM tasks that should be done. • Task frequency could be more effective particularly in the mechanical area. • Some job descriptions were not specific or reflective of actual work. • Identified a opportunities for reliability engineering.

  8. Opportunities Identified…cont • Better utilisation of maintenance and operations resources by eliminating task duplication. • The maintenance strategy needs to be better documented so that it can more easily be reviewed and communicated. • There is an opportunity to transfer some of the knowledge to other processes and sites.

  9. Outcome PM Optimisation Analysis

  10. Outcome PM Optimisation Analysis

  11. Downtime Analysis-Mechanical

  12. Downtime Schedule

  13. Some interesting issues • Some valve failures could possibly be managed by condition monitoring rather than in breakdown. • Breakdown history was recorded incorrectly. This precludes any efficient analysis. • Some task were carried out too often…others not often enough. • The existing mechanical PM were difficult to complete but now broken into three PM’s. • Not all process tech inspections are recorded.

  14. Some interesting issues….cont • Greater involvement of process tech’s in fault finding is possible for maintenance and operations problems. • The justification for each maintenance task is now documented. • The existing PMs are not all being completed. • Pizza Hut do not deliver on public holidays.

  15. Other benefits... • More knowledgeable and empathetic workforce. • More descriptive tasks with acceptable limits. • Improved team work. • Greater sense of ownership in the maintenance and equipment performance. • Better understanding of failure modes and objective of tasks • Planned downtime reduced (1hr per fortnight per unit). • Unplanned downtime will add to this.

  16. Benefits..con’t • Move to a less reactive environment by adopting more frequent inspections where warranted. • The PM program can now be achieved.

  17. What needs to happen now • Input changes to SAP (already started). • Implement the Process Tech check procedure. • Modify Elect Maintenance Tech check sheets. • Develop Mech Maintenance Tech check sheet. • Improve failure reporting in SAP. • Carry out some minor plant modifications. • Implement new tasks ie NDT and Structural inspections .

  18. Improved Reliability through PM Optimisation • Project Team: • Electrician • Planner • Mechanic • Operator • Reliability Engineer Facilitator: Steve Turner