An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tulsa Fuel & Manufacturing Superfund SiteProposed Plan for Site Cleanup

  2. Site Location • Located 1.3 miles south of downtown Collinsville • 60 acres • Bounded by: • Garnett/RR to east • Strip mine pit to south • Acreage to west • Faith Assembly Church to north

  3. Site History 1914-1925: Active Zinc Smelter and Lead Roaster 1999: Listed on the National Priority List (NPL) 2008: Record of Decision (ROD) issued February 2, 2015: Proposed Plan announced

  4. Areas that Require Cleanup • Pink - areas that require cleanup • Green - areas that do not require cleanup • COCs include arsenic, cadmium, and lead

  5. Proposed Plan for Cleanup • Consolidation and capping of soil, sediment, and waste materials on-site • Remedy will not include: • Five-foot vertical separation between waste and groundwater • Stabilization of waste • Proposed Plan remedy offers equivalent protection

  6. Cleanup Goals • Protect human health and the environment • Impacts above cleanup goals and visual smelter waste will be addressed

  7. Site Design

  8. Site DesignStormwater Management

  9. Tentative Schedule • Procurement of a Contractor – 30 to 60 days • Pre-Construction Tasks – 45 days • From Mobilization to Substantial Completion of On-site Activities – 10 months

  10. Activities during that 10 month period • Site Mobilization • Clear and Grub • Soil and Sediment Erosion Control • Decontamination Area • Dewatering the Ponds • Waste, Soil, and Sediment Consolidation • Confirmation Sampling • Remove Existing Wells/Install O&M Wells • Site Grading and Seeding • Demobilization

  11. Protective Elements • Health & Safety Plan • Transportation Plan • Decontamination Plan • Dust Suppression Plan • Site Management Plan • Stormwater Management Plan

  12. Site at Completion

  13. Perimeter Sign

  14. Operation and Maintenance

  15. Locations to review site documents: • Collinsville Public Library • Oklahoma Department of Environmental Quality • Central Records Division • http://www.deq.state.ok.us/lpdnew/SF/TulsaFuels.htm • United States Environmental Protection Agency

  16. Your input on the Proposed Plan is important to us Ways to Comment on the Proposed Plan: • Orally at tonight’s meeting • By Letter to: ODEQ, Rachel Hanigan, 707 N. Robinson, P.O. Box 1677, Oklahoma City, OK 73101-1677 • By Email to: rachel.hanigan@deq.ok.gov or torres.michael@epa.gov Comments must be postmarked or emailed by Monday, March 2, 2015.

  17. Questions or Comments?