Challenges Presented by Brownfield Sites to Major Projects. Berlin, Germany. Annraoi Caffrey, ESBI Project Manager & Finbarr Quigley, ESBI Senior Consultant. 30th March 2012. ESB International in brief…. A multi-disciplinary engineering, consultancy and O&M business 1,100 employees
E N D
Challenges Presented by Brownfield Sites to Major Projects Berlin, Germany Annraoi Caffrey, ESBI Project Manager & Finbarr Quigley, ESBI Senior Consultant 30th March 2012
ESB International in brief… • A multi-disciplinary engineering, consultancy and O&M business • 1,100 employees • Annual turnover approx €110m • Projects completed in 115 countries • Current operations in >20 countries • Wholly owned by ESB Group (Irish state-owned) 35 Year Track Record in International Consultancy
ESBI Recent Projects • Dublin Bay Power, Ireland • 412MW CCGT • Commercial Operation 2002 • Brown Field • Amorebieta, Spain • 755MW CCGT • Commercial Operation 2005 • Green Field
ESBI Recent Projects • Coolkeeragh, Northern Ireland • 400MW CCGT • Commercial Operation 2006 • Brown Field • Marchwood, Southampton UK • 840MW CCGT • Commercial Operation 2009 • Brown Field
ESBI Recent Projects • Aghada, Cork, Ireland • 435MW CCGT • Commercial Operation 2010 • Brown Field • Carrington, Manchester, UK • 860MW CCGT • NTP 2012 • Brown Field
Good infrastructure connection • Gas Transmission System • HV Grid • Transport Routes • Residual Site Risks • Contamination • Existing services and structures • Disruption to existing industrial stakeholders • Cooling • Existing Cooling Source • Reduced Capex • Environmental • Suitable for CCR/ S • Availability of land Benefits vs Challenges of Brown Field • Good planning context • Reusing Brownfield Site • Industrial zoning • Visual impact • Regeneration 800-1500MW CCGT
WaterSource Gas Supply HV Substation Site Overview
Key Challenges Experienced • Route for Gas Pipeline • Existing Buried Structures • Contamination • Invasive Plant Species
Routing of Gas Pipeline
Power plant site Pipeline • 2.4km • Welded steel • 600mm dia • 19.1mm thick • 70barg Carrington Gas Supply
Canal Landfill Culverts Canal Culvert
Canal Landfill Culverts Canal Landfill Culvert Canal Culverts
Canal Landfill Culverts Canal Culvert
Horizontal Directional Drill Ground Level Entry Culvert Structure Exit 30m 1200m long drill Bedrock
Pipeline Outcome • Financial Commitment prior to Financial Close • Engineering Resource Requirement • Extension of Develop Phase Programme • Pipeline detailed design contract • Proved viability of pipeline route • Detailed design available • Significant Saving on Pipeline Construction Contract relative to Design & Build • Risks addressed thus reducing Client’s exposure (time & cost) • Project Value Increased Risks successfully addressed prior to award of fixed price construction contract
Buried Structures - Identifying - Removal - Mapping
Site Issues • Existing foundations supported on piles • Inadequate drawings of foundations • Very limited information on ground conditions • Contamination Issues • Localised hotspots • Japanese Knotweed • Asbestos • Existing HV cables and drains crossing the site
Solution Options • Option 1 • Include in EPC Contract scope • Single all inclusive contract Option 2 Prep work in advance of the EPC Contract Client invests upfront to manage risk • Option 2 Selected with the following objectives: • Provide Information for EPC Contract Negotiation • Prepare Site for handover to EPC Contract
Additional existing piles -Original estimate 3,500 - Final total 5,579
Proven Methodology Risk Workshops Project Risk Logs Geotechnical Risk Log Lessons Learnt Reviews & Log Safety Workshops Zero LTI Goal Safety Initiatives Interactive Safety Workshops with Contractors High Level Steering Committee Contract Delivery
Buried Structures Outcome • Financial Commitment prior to Financial Close • Engineering Resource Requirement • Extension of Develop Phase Programme • Significant Saving on Cost relative to that proposed by EPC • Significant Variation in scope • Risk addressed thus reducing Client’s exposure (time & cost) • Proposed Design now Site Specific • Site Value Increased Risk successfully addressed prior to award of turnkey fixed price contract
Conclusion Experience Lessons Learned Project Delivery Methodology Advance Works Robust Project Risks mitigated Fixed price construction contracts
Thank You Any Questions?