IRFU site report Pierrick Micout CEA/DSM/IRFU
News from Saclay (IRFUonly) Use of the CC-IN2P3 New computing room IRFU local computing IRFU GRIF sub site Network Windows news HEPiX Fall 2011
Centralized (scientific) computing Inside IRFU, the HENPcommunity is using CC-IN2P3 since 1993 as main computing center. HEPiX Fall 2011
New computing room Extension of the liquid cooling Use the 3 Emerson chillers installed for the GRIF IRFU computing room 4 liquid cooled racks Schroff 2 for a new HPC cluster (not yet installed) 1 for Windows 1 for the GRID storage HEPiX Fall 2011
Local computing New NFS storage : Fujitsu Primergy RX 300 S6 AXUS disk array 24*2TB SAS disks SAS 6Gb/s New GPFS storage : 2 DELL PowerEdge R710 2 DELL PowerVault MD3200 12*2TB SAS disks SAS 6 Gb/s 2 DELL PowerVault MD1200 12*2TB SAS disks SAS 6 Gb/s HEPiX Fall 2011
IRFU GRIF sub site To fulfill our pledge 2012 for LHC: 768 TB more storage : 15 DELL R510 : 2 Intel 5630 12 disks SAS 2 TB Broadcom 2*10Gb/s 17 Disk arrays MD1200 : 12 disks SAS 2TB, RAID 6 6 DELL C6100 : 2 X 2 Intel(R) Xeon(R) CPU E5620@2.27GHz 36 GB memory 2 switches GNODAL GS 7200 72 ports 10Gb/s each HEPiX Fall 2011
Network • Discussions on LHCOne: • Dynamic routing • Saclay “datagrid” router • New VLAN • Participants : • RENATER (NREN) • IN2P3 (CC+LAL) • CEA (DSI, Saclay central services and IRFU) HEPiXFall 2011
Windows news @IRFU Microsoft EXCHANGE 2010 : Migration from Exchange 2003 New centralized servers at CEA level 50 first users migrate 11/10/2011 All others users (2000) will migrate in November Synchronization between the 3 AD domains of CEA with Microsoft Forefront Identify Manager (FIM) Hyper-V Cluster Creation of a hyper-V Windows 2008 R2 cluster 2 nodes 15 virtual servers HEPiX Fall 2011