ENGM91 ACTIVITY PLANNING Unit 2. Introduction 1. The unit will cover Work breakdown structure (WBS) Product breakdown Structure (PBS) An introduction to system modelling Precedence analysis Gantt Charts PERT / CPA On Arrow Networks Precedence Networks Also …..
E N D
Introduction 1 • The unit will cover • Work breakdown structure (WBS) • Product breakdown Structure (PBS) • An introduction to system modelling • Precedence analysis • Gantt Charts • PERT / CPA • On Arrow Networks • Precedence Networks • Also ….. • Microsoft Project will be covered in labs • This is based on Gantt Charts and Precedence Networks
Introduction 2 • Activity Planning will help to: • ensure that the appropriate resources will be available precisely when required • avoid different activities competing for the same resource at the same time • produce a detailed schedule showing which staff carry out each activity • Produce a detailed plan against which actual achievement may be measured • produce a timed forecast • re-plan the project during its life to correct drift from a target
Work Breakdown Structure (WBS) • WBS is the decomposition of work into progressively smaller and smaller chunks of work. • The logical conclusion is when work cannot be usefully broken down any further for the tasks being undertaken
Work Breakdown Structure Project Conduct Investigation Produce Report
Work Breakdown Structure • Top Level Project • Level 1 Conduct Investigation
Work Breakdown Structure Conduct Investigation Conduct interviews Investigate other systems Analyse requirements Investigate hardware
Work Breakdown Structure • Top Level Project • Level 1 Conduct Investigation • Level 2 Conduct Interviews
Work Breakdown Structure Conduct interviews Managing director Finance director Stores manager Sales manager
Work Breakdown Structure • Top Level Project • Level 1 Conduct Investigation • Level 2 Conduct Interviews • Level 3 Interview Managing Director
Work Breakdown Structure Interview MD Conduct interview Write and review notes Create data flow diagrams Review data flow diagrams
Work Breakdown Structure • Top Level Project • Level 1 Conduct Investigation • Level 2 Conduct Interviews • Level 3 Interview Managing Director • Level 4 Conduct Interview
Product Breakdown Structure (PBS) • Similar to WBS • PBS is the break down of a product into it’s discrete components. • a PBS can be included as part of a WBS
Product Breakdown Structure (PBS) • An example pbs – taken from a US MIL handbook
System Modelling • Start/End • Activity • Wait • Decision
Flow Chart Exercise • Working in pairs produce flow chart that shows how you would make a hot drink. • This could be: tea, coffee, chocolate or any other hot drink that your team agrees. • The flow chart should ideally cover only one side of A4. You will be provided with A4 paper. • When complete you must scan your flow chart and email to me. • You will be given the time allowed in class.
System Modellinganother view • IDEF0 ... figure 1 is take from the original official IDEF0 manual.
WBS and PBS • WBS, PBS and system modelling will assist in an understanding of the project • WBS and PBS must be done to allow Precedence analysis to take place • WBS and PBS do not necessarily set the precedence of a project • Precedence within a project should be based on what is best for the timely and economic completion of the project
Precedence analysis • Must be done before an activity plan can be produced • Reviews the activities that are to be carried out • Decides what activities must be carried out before particular activity can start
Gantt Charts • Developed by Henry Gantt, around 1917 • Gantt charts are easy to use and produce • They are very useful for use on less complex projects • Commonly used due to there simplicity • Gantt charts are easily understood and easy to read
Gantt Charts • Developed by Henry Gantt, around 1917 • Gantt charts are easy to use and produce • They are very useful for use on less complex projects • Commonly used due to there simplicity • Gantt charts are easily understood and easy to read
Gantt Charts • Draw the following Gantt chart Tasks Precedence Time a - 5 days b - 4 days c a 6 days d b 2 days e b 5 days f c,d 8 days
Network planning models • PERT • The Program Evaluation and Review Technique • Developed by: • US Navy with • BOOZ-Allen Hamilton and • Lockheed Corporation for the • Polaris missile/submarine project in 1958
Network planning models • CPM • Critical Path Method • Also know as CPA • Critical Path Analysis • Developed by • DuPont Inc in the • Late fifties early sixties to facilitate • building of complex process plant
Network planning models • PERT • developed for use on R&D projects • CPM • developed for use in construction projects • When developed the two techniques were very similar • Now there is virtually no difference between the two
d 2 a g 5 e b End Start 1 5 3 h c f 5 4 Network planning models • A simple on arrow network model
Terminology • Activity • A specific task, uses resources takes time to complete • Event • The result of completing an activity • Events use no resources • They are instances in time, points on the network, conditions of a system that can be recognised
Terminology • Network • The combination or all activities (often drawn as lines) and events (often drawn as nodes at the beginning and end of each line) defines the project and the activity precedence relationship. • Arrow heads placed on the lines indicate the direction of flow. Before and an event can be realised all the activities that immediately precede it must be completed
Terminology • Path • The series of connected activities (or intermediate events) between any two events in a network • Critical • Activities, events, or paths, which, if delayed, will delay the completion of the project • A project’s criticalpath is understood to mean that sequence of critical activities (and critical events) that connect the project’s start event to its finish event
2 C=3 A=6 6 3 H=2 4 1 D=4 B=4 E=3 G=3 5 F=10 Terminology • On Arrow Network diagram showing critical path in red
Network syntax • Time moves from left to right • Nodes are numbered sequentially • A network may not contain loops • A network may not contain dangles • Precedents are the immediate preceding activities • Dummy activities can be used to indicate a particular precedence
a b 1 2 3 Network syntax • Time moves from left to right • Nodes are numbered sequentially
4 d c a 1 2 3 b This is not allowed Network syntax • A network may not contain loops
b a 1 2 3 c 4 This is not allowed Network syntax • A network may not contain dangles
Design Build Commission 1 2 3 4 Network syntax • Precedents are the immediate preceding activities
a c Wrong 1 2 3 b a 2 1 Right c b 3 4 Network syntax • Dummy activities can be used to indicate a particular precedence
On Arrow Networks • Draw the following as an on arrow network Tasks Precedence Time a - 5 days b - 4 days c a 6 days d b 2 days e b 5 days f c,d 8 days
2 a start 1 b 3 On Arrow Networks • How to start …..