MAE 435 Progress Report. 2/19/13. MAE 435W. Facebook/twitter Shop clean-up Marketing meetings Engineering/club o pen houses Printed and reviewed rule b ook. Aerodynamics Team. Mock-up/measurements Input designs (SolidWorks ) Created clean r oom (Fiberglass work)
E N D
MAE 435 Progress Report 2/19/13
MAE 435W Facebook/twitter Shop clean-up Marketing meetings Engineering/club open houses Printed and reviewed rule book
Aerodynamics Team Mock-up/measurements Input designs (SolidWorks) Created clean room (Fiberglass work) Inventory safety equipment Created budgets
Chassis Team • Created front suspension: • Control arms • Uprights • Spindles • Created rear suspension: • 4 new points (shorten control arm length) • New brackets (to reuse previous uprights) • Designing brake mounts • Created Steering Column/Rack and pinion mount
Powertrain Team Engine mounting Oil pan design and fabrication Cooling system Differential mount Intake Fuel system