50 likes | 178 Views
MAE 435 Progress Report II. 4/2/13. MAE 435. Raising Canes Fundraiser (over $180) Panda Express Fundraiser (over $150) Very Generous Donation From Dr.Chaturvedi ($2). Aerodynamics Team. Finalizing nose cone mold ( XVD longboards) Analysis was completed on body panels (~63% lighter)
E N D
MAE 435 Progress Report II 4/2/13
MAE 435 • Raising Canes Fundraiser (over $180) • Panda Express Fundraiser (over $150) • Very Generous Donation From Dr.Chaturvedi ($2)
Aerodynamics Team • Finalizing nose cone mold (XVD longboards) • Analysis was completed on body panels (~63% lighter) • Side pods are completed • Next step will be fabricate nose cone and assemble body panels
Chassis Team • Fabricated front & rear brake caliper mounts • Fabricating shifter & pedals • Waiting on L&W parts • Completing welding of entire frame
Powertrain Team • Exhaust System is 100% Complete • Wiring is 80% Complete • Fuel system is 60% Complete • Differential / Rear Brake Rotor are 100% Complete • No progress on Air Intake