Project Purpose • What we are doing? • Producing syngas from petcoke • Using entrained flow gasifier • Implementing a rigorous syngas cleaning • Why we are doing this? • Making syngas for acetic acid production • Chemical production team specs • CO to H2 molar ratio of 0.409 • CO2 and N2 mixed in http://coalgasificationnews.com/tag/petcoke-gasification/
Recap • Discussed the Shell™ membrane gasifier • Discussed our syngas processes • Sulfur Removal • Claus Process • Water Gas Shift • Flow Sheets • Early Material and Energy Balances
Questions Brought Up Last Time • Why use N2 as a transport gas and not CO2? • How are we absorbing CO2?
Agenda • Recent changes • Using Selexol instead of MDEA • Using the Superclaus • Aspen Simulation • Heat Load Identification • Economics • Aspen Price Evaluator (ICARUS) • Equipment Sizing • Location Update
Flow Sheeting: Overall Process Gasification Sulfur Removal Claus Process Water Gas Shift CO2 Removal
Flow Sheeting: Gasification To Sulfur Removal
Flow Sheeting: Sulfur Removal To Claus To WGS
Flow Sheeting: WGS & CO2 To Chem Production Capture Ready CO2
Flow Sheeting: Claus Process To Superclaus
Heat Sink Optimization • Stream Pre-heating • Lower Heater / Cooler Duties • Heat Duty and Heat Ex. Cost Tradeoff Cold Furnace Gas Acid Gas Cold Acid Gas Hot Cooler HX Furnace To Claus Catalysts Hot Furnace Gas
Solid Removal Gasification Price $240,306,575 Sulfur Removal Economics and Size Claus Process Final syngas product CO2 Absorption WGS Reactor
Solid Removal $670,000 Gasification Price $240,306,575 Sulfur Removal EquipmentCostandSize Cont. Claus Process CO2 Absorption WGS Reactor Final syngas product
Solid Removal $670,000 Gasification Price $240,306,575 SulfurRemoval $9,600,000 EquipmentCostandSize Cont. Claus Process CO2 Absorption WGS Reactor Final syngas product
Solid Removal $670,000 Gasification Price $240,306,575 Sulfur Removal $9,600,000 Claus Process $12,500,000 EquipmentCostandSize Cont. CO2 Absorption WGS Reactor Final syngas product
Solid Removal $670,000 Gasification Price $240,306,575 Sulfur Removal $9,600,000 EquipmentCostandSize Cont. Claus Process $12,500,000 CO2 Absorption $35,700,000 WGS Reactor Final syngas product 144 ft3 $360,000
Solid Removal $670,000 Gasification Price $240,306,575 Sulfur Removal $9,600,000 Overall Summary of Capital Cost Claus Process $12,500,000 CO2 Absorption $35,700,000 WGS Reactor 144 ft3 $360,000 Final syngas Product $300,000,000
Other Fixed Cost Capital Cost as of now= $ 300,000,000 Labor Cost as of now = $ 24,000,000
Overall Expenses Capital Cost as of now = $ 300,000,000
Location • Victoria, Texas • Between Houston and Corpus Christi • 200 acres • Kansas City Southern, Union Pacific, and Burlington Northern Santa Fe railways • Gulf Intracoastal Waterway
Possible Alternatives • Alberta, Canada • Sits on excess petroleum coke from refineries • Is it Economically viable? • Demand • Transportation costs
Conclusion • Overall ASPEN procedure • Gasification • Syngas Clean Up • CO2 Removal • Rough Economics • Location: Victoria, Texas • Possible Change
Next Steps • Final process flow diagram • Control scheme • Optimize economy scale • Revise capital costs • Major equipments list and plant layout • Revise report
References • http://fossil.energy.gov/images/programs/sequestration/what_sequestration_lg.jpg • http://coalgasificationnews.com/tag/petcoke-gasification/ • http://www.huffingtonpost.com/dr-orin-levine/questions-as-mileposts-of_b_448870.html • http://www.chinaep-tech.com/upload/accessary/8173/DZY08092502.pdf • http://www.chemicals-technology.com/projects/gulfpetrochemicalsco/
Report Outline • Final Report: • Executive Summary IP • Discussion IP • Recommendations IP • Appendices • Design Basis: Done • Block Flow Diagram: Done • Process Flow Showing Major Equip.: IP
Report Outline • Appendices (Continued) • Material and Energy Balances: IP • Calculations: IP • Annotated Equip. List: IP • Econ. Eval. Factored from Equip. Costs: IP • Utilities: IP • Conceptual Control Scheme: N/A • Major Equipment Layout: IP
Report Outline • Appendices (Continued) • Distribution and End-use Issues: IP • Constraints Review: IP • Applicable Standards: IP • Project Communications File: IP • Information Sources and References: IP
CO2 Sequestration • CO2 in our syngas is absorbed on Selexol to be selectively removed • Delete only one CO2 slide.
http://fossil.energy.gov/images/programs/sequestration/what_sequestration_lg.jpghttp://fossil.energy.gov/images/programs/sequestration/what_sequestration_lg.jpg