This detailed plan outlines the need for a Construction Manager & General Contractor (CM/GC) and the rigorous selection criteria including safety records, experience, and financial strength. It covers preconstruction and construction activities, subcontractor procurement, and specifics of project management, safety, and quality assurance. The plan also highlights the project scope including underground and above-ground facilities for the LCLS project.
E N D
CM/GC Overview CM/GC Plan & Status Systems Description Cost Estimate Construction Schedule Risks and Challenges Summary
CM/GC Plan • Why do we need a CMGC (Construction Manager & General Contractor) • SLAC does not have the in-house expertise to independently manage a project of this magnitude
CM/GC Plan • SOW for CM/GC has been developed and continues to have the highest priority in the CF group as largest stand-alone procurement in the LCLS project • Currently being reviewed by SLAC SO DOE • Comments being updated as we speak • Once approved by SLAC SO DOE, the plan is to submit to DOE Headquarters for approval (Chicago → DC) • Once plan is approved, there will not be a need to go back for multiple review and approval of bid packages
CM/GC Plan – cont’d Advertisement placed in construction periodical – ENR Magazine Jan/Feb • Advanced Procurement Plan (APP) has been written and continues to be updated as necessary (signed copy on LCLS website) Meeting planned Milestones are crucial!
CM/GC Plan – cont’d • CM/GC services will be solicited as firm-fixed price contracts • Phase 1 – preconstruction services • Phase 2 – construction services of underground and major excavation effort, and construction services of above ground buildings • CM/GC Award 6/30/05 • CM/GC qualifications – partial list • Technical competence • Similar previous experience • Successful history using second and third tier subcontractors • Financial strength
CM/GC Plan – cont’d • Outstanding safety record • Experience Modification Rate (EMR) <.81 • EMR 1.0 indicates that a company submits injury claims that are considered average among their industry group • EMR > 1.0 indicated that the company files more claims than other similar companies • EMR<0.81 indicates that the company had filed fewer claims than those compared against similar companies • Injury frequency and severity rates • Safety Program evaluation and evaluations of the key personnel • OSHA citation history • References from previous projects • Evaluation of the contractors’ integration of safety into their work practices LCLS has decided to place all contractors working on projects to have an EMR of <.81, go no-go
CM/GC Phase 1 Effort • Phase 1 – preconstruction activities to include: • Provide effective overlap period and oversight of effort during Title II • Estimates during Title II • CPM Schedule • Identify lead-time for critical items • Design coordination • Constructability reviews • Value Engineering reviews • Site investigation
CM/GC Phase 1 Effort – cont’d • Develop Project Management Plan (PMP) • Construction Management Plan – outlines project scope, organization, and specific approach to accomplish project • Project Safety Plan – project specific identifying job hazards, safety performance and individuals responsible for project safety • Procurement Plan – identifies systems, methods and procedures for solicitation to subcontractors • Quality Control and Assurance Plan – method of controlling time, cost and quality of various management tasks specific to the project
CM/GC Phase 1 Effort – cont’d • Develop construction bid packages • Develop list and contact potential bidders • Develop prequalification criteria • Solicit bids • Recommend award to SLAC for approval of subcontractor • Award contract to subcontractors
CM/GC Phase 2 Effort • Phase 2 – CM/GC shall provide all materials, labor, and services required to construct the Project • All general conditions including field personnel, office staff, temporary offices, temporary construction, safety implementation, construction equipment, coordination of all subs, project administration, construction waste management, commissioning
Below Grade Plan Beam Transport Hall Near Hall Undulator Hall XRTDT Far Hall
New Facilities (below grade) • Beam Transport Hall – 227m long above grade facility to transport the electron beam through the existing RSY • Undulator Hall – 175m long underground tunnel housing undulators and ancillary equipment • Central Lab Office Complex – office facility to house ~ 300 LCLS researchers, engineers, technicians, administrative staff and visiting experimentalists • Far Experimental Hall – underground cavern/tunnels to house 3 experimental hutches, prep and shop space • Electron Beam Dump – 40m long underground facility used to separate the electron and x-ray beams • Front End Enclosure – 30m long underground facility to house various diagnostic equipment in support of the photon beam • Near Experimental Hall – underground facility whose primary function is to house 3 experimental hutches, prep and shops • X-Ray Transport & Diagnostics Tunnel – 250m long underground tunnel used to transport photon beams from NEH to FEH
LCLS Site Plan Spear Future Office Space Pep Ring Road SLC Office Complex Undulator Hall Research Yard Survey Tower NEH Beam Transport Hall SLC Tunnel Beam Dump Front End Enclosure Future Beam Lines X-Ray Transport Pep Tunnel
BEAM TRANSPORT HALL • IN RESEARCH YARD • 227 M LONG • 15’ x 14’-9” (W x H) • 63 M HEADHOUSE • 72” THICK WALLS • 48” THICK CEILING • 3 SERVICE AREAS • ENDS IN HEADWALL • HEADWALL LABYRINTH
BEAM TRANSPORT HALL UNDULATOR HALL • UNDER HILL • 175 M LONG • 21’-11” x 14’-6” (W x H) • 33 UNDULATORS • HEAVY GRANITE SLABS • MONOLITHIC FLOOR • THERMAL BARRIERS
BEAM TRANSPORT HALL UNDULATOR HALL ELECTRON BEAM DUMP • UNDER PEP RING RD. • 40 M LONG • 15’ x 12’-6” (W x H) • CAST-IN-PLACE • GROOVED FLOORS • E-BEAM DIPS DOWN • HEAVY METAL SHEILD
BEAM TRANSPORT HALL UNDULATOR HALL ELECTRON BEAM DUMP FRONT END ENCLOSURE • EAST OF BEAM DUMP • 29 M LONG • BETWEEN SHEILDS • 15’ x 12’-6” (W x H) • CAST-IN-PLACE • NUMEROUS EQUIP.
FRONT END ENCLOSURE UNDULATOR HALL ELECTRON BEAM DUMP NEAR EXPERIMENTAL HALL BEAM TRANSPORT HALL • EAST OF FEE • 39 M LONG • 2 FLOORS • 3 HUTCHES • LASER BAY (ABOVE) • CLOC FACILITY ABOVE • PREP & CONTROL AREA • FREIGHT ELEVATOR • CUT & FILL TECHNIQUE
FRONT END ENCLOSURE UNDULATOR HALL ELECTRON BEAM DUMP NEAR EXPERIMENTAL HALL NEH HUTCHES BEAM TRANSPORT HALL • WITHIN NEH • TOTAL 3 (CURRENT) • ANOTHER 3 (FUTURE) • 10 M x 10 M • SHEILDING NEEDED • HEAVY SLIDING DOOR
FRONT END ENCLOSURE NEAR EXPERIMENTAL HALL UNDULATOR HALL ELECTRON BEAM DUMP BEAM TRANSPORT HALL X-RAY TRANSPORT TUNNEL • EAST OF NEH • 250 M LONG • 18’ WIDE CONSTANT • BEAM SPLITS IN THREE • LABYRINTH TO FEH • WALKWAY ALONG BEAM
FRONT END ENCLOSURE NEAR EXPERIMENTAL HALL X-RAY TRANSPORT TUNNEL UNDULATOR HALL ELECTRON BEAM DUMP FAR EXPERIMENTAL HALL BEAM TRANSPORT HALL • END OF X-RAY TUNNEL • 29 M LONG • 2 CAVERN/TUNNELS • 31’ x 21’ (W x H) • CONNECTING TUNNELS • OFFICES IN EXTENDED CAVERN • ACCESS TUNNEL
CLOC Floor Plans CLOC Exterior Elevations • Headcount of CLOC Personnel = 284 • Capacity of Conf Center = 150 • Gross square footage of CLOC (offices and labs) = 68,800sf
CF FY Total Estimated Cost CMGC is responsible for ~$500K for Phase I (Award CMGC thru March 06) and $59.5M for Phase II (Mar 06 thru 08)
LCLS CF Construction Schedule • Added additional time for CM/GC procurement phase: • DOE approval and CM/GC subcontractor bidding phase • Major construction phase FY 06 at 30 months duration • Beneficial Occupancy dates are key to technical system interfaces • Site-work at NEH is key!
Title-II Draft Schedule Interactive Planning session is scheduled for April 13,14 (6/05) CMGC has real value added input early during design phase This is essentially JE 100% stage
Risks and Challenges Construction Safety All construction activities to comply with Federal and State environmental, safety, health and building codes Subcontractor activities In-house activities SLAC will approve construction safety program prior to start of construction Enhanced construction program is a must Special consideration is being addressed Tunnel construction RSY due to the congestion in the area
Risks and Challenges – cont’d Bay area construction market Materials Labor Schedule concerns Annual lab shut-down periods Schedule for site characterization & remediation FFTB decommissioning On-site support
Summary Confidence is high for the successful implementation of the model chosen as it has already been proved at LBNL Molecular Foundry CMGC holds the paper Actual cost will be determined by competitive bids from subcontractors Total estimated pricing established by SLAC
Additional data All subcontractor bids and award of contracts will be pre-approved by SLAC Subcontractor bid award amounts added to CM/GC contract Technical Documents: CM/GC Statement of Work General Requirements (01010) Special Requirements (01210) Schedules (01325) Construction Waste Management (01570) Schedule of Performance Milestones