70 likes | 225 Views
X-Ray Calorimeter Mission Study Summary. Team Lead Mark Steiner 2 – 6 April 2012. X-ray Cal Presentation Timeline. MDL Mission Study Summary. MDL developed mission concept for calorimeter configuration, based on customer inputs
E N D
X-Ray Calorimeter MissionStudy Summary Team Lead Mark Steiner 2 – 6 April 2012
MDL Mission Study Summary • MDL developed mission concept for calorimeter configuration, based on customer inputs • MDL team presented formal, final report out to customer team • Presentations were reviewed by MDL team for internal consistency on Thursday • Delta options identified for last X-ray mission study (“Delta” week) • TBD - Decision to be made at later date by customer team
Mission Summary – Final (same as Monday) Orbit parameters – L2, 800,000 km Lissajous LV – Falcon 9 Launch date – March 25, 2022 Mission Lifetime – 3 year minium / 5 year goal Mass estimate – payload: 221 kg (Instrument) 319 kg (X-Ray Mirror) – 540 kg total Power estimate – payload: 686W (Instrument) , 320 W (X-Ray Mirror) – 1006 W total Mission class –B Disposal plans – Same as Grating Mission ( 1 m/s delta-V at EOL) Study name: MDL X-ray Grating WBS: 244904.04.10.01.02 ”MDL X-ray Cal” in remarks
MDL Areas of Concentration/Study Drivers • Use of Solar Panels to balance CP-CG offset • Adapt AXSIO inner Mirror purge cover for this SC concept • Need for heater power on the SC structure adjacent to FMA to maintain FMA thermal requirements If possible… • Increase pitch to +/-45 trade for articulated solar panel
Study Plan for the week • Monday AM: review study expectations and identify key issues PM: 1) define ConOps 2) discuss derived subsystem requirements and ask questions • Tuesday AM: System drivers – TBD subsystems PM: Rest of subsystems • Wednesday AM: I&T Flow, Mission Ops PM: Presentation preparation • Thursday AM: Check presentations for consistency PM: Finish presentations • Friday Presentation with customers, including remote customer team • Monday following 1) Lessons learned, process improvements, lab status, etc. 2) Finalize presentations and wrap up the study
X-Ray Calorimeter Program flow Mission Critical Design Review (CDR) 2/13/2019 ATP - Phase B Start S/C Bus 9/1/2016 Preliminary Design Review (PDR) 11/22/2017 S/C Bus Contract Award System Definition Review (SDR) Project Start ~ 8/8/2014 Phase A Preliminary Analysis Phase B Definition and Prelim Design Phase C Final Design Preliminary Design Mission Definition System Definition Final Design 16 “months” 24“months” 16“months” End of Extended Mission 6/25/2027 End of Primary Mission 6/25/2025 Instrument Delivery FMA: 12/8/2020 XMS: 2.26/2021 Launch 3/25/2022 Transition To Nominal Ops 6/25/2022 Ready to Ship 10/8/2021 Phase D-1 Subsystem Development, S/C Integration & Test, Launch Prep Phase D-2 Launch & Checkout Total Funded Reserve Phase E/F Operations Fab., S/C Assy & Func. I&T 19mo’s Prep for Launch 3mo’s Obser. I&T 11mo’s Cruise, Orbit Insertion & Checkout PrimaryMission Extended Mission ? 7.5 months Launch (Spread through Phases C & D) 33 “months” 36 months 24 months 3months Notes: Timeline not to scale; 1 “month” = 28 days.